RFQ test stand (long term) BI developments
Present: Federico Roncarolo ; Giulia Bellodi <; Jean-Baptiste Lallement ; Edgar Sargsyan , Richard Scrivens
We will now operate RFQ2 test bench (with RFQ ready in Aug-Sep 2025). All is ready for this (RFQ BCT and BPM to be installed when RFQ2 moved in final position)
Test bench upgrade document written in 2020 is here:
RFQ_Test_Stand_Future_Proposal_v3_docx_cpdf.pdf
MTP2025 approved full package (basically reallocating budget from RFQ3 production which was canceled)
For BI it is:
Item |
Budget |
Details |
2 x BPMs for ToF |
60kCH |
"standard" L4 BPM with "standard" DAQ for ToF (present BPM used only via scope for phase meas) |
3MeV EM consolidation |
30k |
Assessment planned for autumn when RFQ test bench starts running |
BI-SW grad |
90k |
Could partially fund new/existing Origin to ensure test bench compatibility with White Rabbit |
BI maintenance |
25k |
For exploitation |
Total budget: 205kCH, in principle available from now
Discussion summary:
- All money is available. We should assess if and how we can use it by defining a budget profile from now to Jan 2028
- RFQ test stand master schedule and BI related tasks:
- Sep-Oct 25 to Sep 26 (operate present test stand)
- Measure RFQ2 from : diagnostics as is, to be maintained
- No new BPM installation possible
- Assume present EM will work
- Oct26-Dec27 (prepare for after LS3)
- Can we envisage providing 2 BPMs with DAQ?
- New BPMs may include integration studies (driven by ABP with BI input as needed)
- Any EM modifications to be assessed from experience starting Sep 25 (EM has not been operated for a while)
- Test stand with White Rabbit after LS3: we must ensure HW and SW compatibility → Is it clear what we need to do for BCT, SEM, BPMs? Do we want to pay 1/3 of an Origin with the 90k available here?
- Federico will:
- Discuss in BI, assess available resources, need for new resources
- Get back to ABP via email in July
- New meeting first week of Sep to agree on reasonable budget profile