· The crane replacement planning was presented:
o No access to the underground during the crane replacement
o The existing crane has to be used until step 5 (Dismantling of the existing crane)
o They are flexible in the intervention period. But the new crane has to be used for the dismantling of the upstream of TCC8.
· (slide 11) Removal of equipment before the intervention
o The separation of the blue door: to be checked if the full door has to be removed or only the top part.
o The fans in the blue door will be compromised:
§ [Action 3] (_____): to check if additional ventilation systems are required for TCC8.
o [Action C. Duran + R. Rinaldesi]: check with the contractor the equipment that need to be removed or protected before the intervention
· Obsolete crane disposal.
o Assumed to be non-radioactive
o There is the possibility to cut it directly in the underground and bring it cut to the overground
· Storage space overground:
o For the moment, 2 weeks of storage of the new crane can be foreseen, but it’s not confirmed yet.
o As soon as the new crane arrives they will transported to the underground