AMBER gas system
background:
[GASSYSTEMS-37] Gas system for AMBER TPC - CERN Central Jira
expected:
Roberto, the estimated time 10 weeks (5 mech/pipe + 5 elec) from drawings last thursday was not divided like you announce. The division will be more 8 weeks of mech/pipes/welds/installation and 2 weeks for electrical if this is enough.
To be confirm on the electrical side by Patrick.
from GASSYSTEMS-312 AMBER TPC gas system manpower - CERN Central Jira
Roberto Guida added a comment - 18/Oct/24 4:24 PM
the conclusion of last meeting (held on october 15th in Patrick's office, present Andrea, Patrick, Fred, Gianluca and Roberto) is:
10 weeks (mech+welding) and 4 weeks electrical if old control rack can be reused. If old control rack cannot be reused, 2 weeks of manpower elec should be added.
Andrea D'Auria Patrick Carrie Please confirm if is right or wrong.
Thanks a lot
--> 10 w (mech+welding) + 4 w electrical
"Today (July 14th, 2025)": AMBER Construction.pdf summary from Andrea
| done (w) | estimated (w) | difference (w) | ||
| mech | 10.44 | |||
| weld | 7.9 | 10 | 8.34 | |
| elec | 7.7 | 4 | 3.7 | |
| 24080 | CHF | |||
| projection from Andrea | ||||
| 25892 | CHF |
Material updated until June25th, 2025
- material 52 k
email with details to OlegD
but new orders are still ongoing