Discussion on the Characterization of AIDAInnova Related Productions
Requested: Second week of the test beam, starting October 8th
- Test beam crew list (PLEASE SUBSCRIBE):
- Test beam detailed equipment and DUT list:
- Zurich Wiki for sensors:
Devices Under Test (DUT)
- TI-LGADs (V1):
- Proposed list of devices from Iskra's talk attached in the indico. Priority: V1.
- Fluence points: 1.5E15, 2.5E15, 0 (from UZH). Need to add and check 0.8E14 sample.
- We need to calculate how much time is required per batch (at least 3 days).
- Assume that one batch can accommodate DUTs for each fluence.
- 3D Devices: Fresh and irradiated 3D-trenched from FBK (AIDAInnova), and DS 3D-columnar from IMB-CNM (RD50).
- Trenched 3D at CERN and irradiated in IRRAD: ~50 structures in 16 samples, equally shared among fluences:
Φ = 1×1016, Φ = 2.5×1016, Φ = 5×1016, Φ = 1×1017
- Unclear how many unirradiated samples are at CERN.
- IFCA will provide the UCSC board to be mounted at CERN.
- Need to confirm status of irradiated CNM columnar 3D samples at JSI (irradiation point, radioprotection clearance).
Front-End
- UCSC boards + second-stage amplifier (per Vagelis’ suggestion: link). To buy the amplifiers.
Note: second stage reduces SNR by approximately ½ according to specifications.
Sample Packaging
- At CERN: mounting 3D-trenched devices on UCSC boards.
- At JSI: irradiated TI-LGADs on Chubut2.
- At JSI: non-irradiated TI-LGADs on Chubut2.
Cold Box Equipment
- Five XY piezo stages for DUT and one additional XY piezo stage for reference sensor.
- Single DUT per frame.
- Suppor frames availability for Chubut2 and UCSC (to locate or/and manufacture)
- Cooling box: request transfer to the H6 area.
- Missing AIDA chiller and water cooler (contact: Andre).
- Need to remove/relocate horizontal aluminum profile of the telescope supporting frame (used as cable tray) to prevent collisions with the cooling box.
- Motorized heavy-duty stages (missing end-of-limit switches):
- Resetting position could move cooling box too far, risking cable and tube breakage.
- Movement remains under expert control (Andre or Vagelis).
- Recommendation: disconnect the large stage after alignment for safety.
Reference Plane
- Design proposed by Vagelis: HPK LGAD + UCSC board + second-stage amplifier feeding two digitizers (via RF splitter).
Power Supplies
- Need to clarify availability of HV power supplies.
DAQ
- TI-LGAD:
- Same DAQ as April 2025 test beam.
- 3D Pixels:
- Proposal: use a Tektronics MS064-6B from the CERN Electronics Pool.
- Suggested arrangement (Vagelis): link.
- Note: no EUDAQ producer available for high-bandwidth oscilloscopes.
- Dedicated meeting required.