Cadence & Process
- New combined BIPXL JIRA board for all Timepix-related projects (BGI, telescope, some BLM/R&D).
- Priorities simplified to High / Medium / Low. First part of each bi‑weekly meeting will review High priority items.
- Next meeting: in 2 weeks.
Key Upcoming Dates
- Telescope test beam starts (effectively) next Wednesday.
- SPS MD with LHC(-like) multi‑bunch beam next Thursday for BGI vs wire scanner cross‑comparison.
- Beam size review: 22 Sept (prepare SPS results).
- Lukas vacation: end of August.
Technical Status & Discussion
- SPS BGI / Beam Size Review
- Horizontal detector “brick with more holes” survived AWAKE-like high-rad beam (bunch rotation / compression).
- Plan: show SPS profile evolution and robustness in review.
- Next Thursday MD: acquire comparative data (BGI + wire scanner).
- Telescope & Timing
- Previous timestamp issue traced to miscalculated fine ToA resolution and wrongly adding the fToA, also GBTXs are now correctly configured.
- Raw Timepix data now plausible; need to validate delayed pixels (~150 ns offsets) vs timewalk or anomaly.
- Observed event rate ~1 kHz (lower than theoretical); need to confirm if readout or configuration bottleneck.
- Closely spaced telescope setup on granite table starts Wednesday (two XY stages, optical rail, two planes per rail).
- Cosmic ray telescope scintillator setup ready; may be optional given imminent beam setup.
- Telescope Infrastructure
- “Home base” relocation mostly done; PPE128 installation updated.
- Minimal test setup operational; system test epic starts next week.
- Need cable length/delay documentation (TDR device hard to use; fallback oscilloscope).
- PS BGI Horizontal Issue
- No ionization electrons detected since Christmas despite correct HV (~30 kV) and bias.
- Findings: ToT plot order non-sequential (fixed); full decode disabled (fixed); ToTs now reasonable; detector 3 still problematic; Ikrum differences likely incidental.
- Hypotheses: sensor surface contamination (near pump), configuration fault, hardware degradation.
- Options: (a) Diagnose current unit (remove, measure HV & bias path conductivities) (b) Assemble and install spare (inventory flex cables, edgeless sensors).
- Constraint: PS geometry—SPS sensor pair may not fit side-by-side; may need more (edgeless) sensors; potential ordering urgency.
- GBTX Configuration Reliability
- New gateware requires running full register config twice to achieve stable sync; first pass yields partial/noisy links.
- Current state machine likely insufficient; ad‑hoc delays (sleep up to 1 s) required.
- Need clearer reset / configuration sequencing and robust completion criteria.
- Software / DMA
- DMA (XDMA) migration mostly done; pending EDGE driver work.
- V5 software meeting to be organized (next week proposed).
Decisions
- Maintain bi-weekly meeting format.
- Proceed with telescope granite-table deployment Wednesday.
- Use Thursday MD for BGI–wire scanner cross-validation.
- Defer extensive cosmic data unless spare capacity.
- Prepare to intervene on PS horizontal if no progress soon (parallel diagnosis + spare assembly planning).
Open Issues / Risks
- Unresolved root cause for PS BGI horizontal (risk to operational readiness).
- GBTX config instability (risk to data quality / automation).
- Low event rate vs expectation.
- Time pressure: need MD data analysis before Lukas vacation.
- Potential sensor supply constraint for PS replacement.
Action Items
|
Action |
Owner |
|
Create JIRA ticket: inventory parts (flex cables, edgeless sensors) & replacement plan for PS horizontal |
James |
|
Analyze Thursday MD data promptly (profiles, cross-check with wire scanner) |
Lukas |
|
Validate delayed pixel clusters (150 ns) vs Timewalk; filter criteria for hit assembly |
Lukas / Hampus |
|
Investigate event rate limitation (readout path, throttling) |
Lukas / Justus |
|
Inventory edgeless sensor stock; assess need/order lead time |
James / Mark |
|
Assemble spare instrument (if parts sufficient) |
James + Mark + Wilfried + Hampus |
|
Prepare granite-table telescope hardware (stages, rails, planes) for Wednesday |
Justus (+ Mark assist) |
|
Document cable lengths & propagation delays (oscilloscope fallback) |
Wilfried / Justus |
|
Refactor GBTX config state machine (deterministic sequencing, remove double-run) |
Hampus |
|
Clarify reset signal usage & document recommended sequence |
Justus |
|
Organize V5 software meeting next week |
Jüri |
|
Continue DMA migration; coordinate EDGE driver integration |
Gabriela / Jüri |
|
Provide pulse generator timing characterization for scintillator reference |
Mark |
|
Send meeting transcript and minutes |
James / Jüri |
Follow-Up Next Meeting
- MD data results & comparison plots.
- Status of PS horizontal diagnostics or replacement decision.
- GBTX configuration reliability improvement.
- Telescope deployment progress & initial timing validation.
- Event rate investigation findings.
- DMA / driver integration status.
End.