Date: 29/08/2025

Participants: James, Mark, Steen, Hampus, Juri, Lukas (Zoom), Gabriela (Zoom)

Key Technical Updates

  • Timing & Synchronization: Current telescope timestamps limited to ±100 ns. TimeWalk correction demonstrated (~10 ns residual). SPS bunch-by-bunch requires <25 ns precision. Next step: SPS BGI calibration using single LHC bunch (1 x 5ns bucket filled) or in the future electron gun.

  • HL-LHC Beam Profile Review (23 Sept): BI contribution: 20-min BGI talk (James) on design, performance, and PS/SPS experience. Results needed before Lukas’ holiday.

  • Telescope: Detector correlations now clear; track χ² improving with ongoing software alignment. Next: reference crystal installation + multi-volume crystal tests.

  • DAQ/FESA Stability: Occasional crashes during MD runs (likely data-volume related). Stable in command-line mode; monitoring continues.

  • Hardware / Optics: Broken fibre in telescope channel traced to installation; procedure should be documented. GBTx configuration improved significantly and seems stable now in 4.1.3-release branch.

  • SPS BGI Vertical: Raw data path non-functional; likely SFP/module issue. Plan: retest in lab post-run with validated SD cards and spares.

Strategic / Forward Planning

  • PCIe/DMA Support: Ongoing difficulties with Edge + XDMA drivers. Options:

    1. Investigate Edge 2.1 compatibility.

    2. Fallback to commercial PCIe cards with supported DMA drivers.
      Decision required within 2 weeks to ensure 2026 PS/SPS BGI readiness.

  • PS Horizontal BGI: Persistent no ionization electron problem. Decision: build new instrument from existing spares; test and qualify before LS3.

  • PS BGI Front-Ends: Failing after minutes due to (probably) thermal problem. Hampus & Wilfried to implement solution with fan. Radiation damage to DC fans could be an issue.
  • SPS Shields: Horizontal now robust with RF shield. Vertical shield upgrade under study (diamond or smaller-hole variant). Decision point: end November. Possible MD to test shield options.

Acknowledgement

  • Farewell to Gabriela (final day). Team expressed gratitude for her 3 years of valuable contributions.

 


Follow-up next meeting

  • Prepare BGI results for HL-LHC review (Sept 23).

  • Build new PS horizontal BGI instrument.

  • Prepare alternative SPS vertical shield (diamond-type).

  • Standardize fibre installation procedures.

  • Continue monitoring FESA crashes.

  • Finalize PCIe/DMA approach by mid-September.

There are minutes attached to this event. Show them.
    • 14:00 14:20
      Status of "High Priority" BIPXL JIRA Issues 20m

      https://its.cern.ch/jira/projects/BIPXL

    • 14:20 15:00
      Topical presentation(s) & discussion 40m