Description
Report on EMI support status
GGUS Dashboard - EMI User support Procedure
Support status report - as of 26.04.2013
- 4 assigned, 0 SLA violations
Ticket closing campaign - announced by MathildeR
Dear EMI product teams, GGUS still holds 178 open tickets for EMI products (22 of them date back to 2011, 67 were filed in 2012). With the release of EMI-3 and its first update release the expectation is that most of the GGUS tickets currently in an open state are solved now and can be closed. Therefore, for each open ticket in the support unit(s) you are responsible for please proceed as follows: - in case a solution has been released with EMI-3, _close_ the ticket as _solved_ - in case a solution will be implemented with the final EMI-3 update release, _comment_ this in the ticket - in case a solution will not be implemented at all, _close_ the ticket as _unsolved_ - in case a solution will be implemented in your product after the end of EMI, _state_ this in the ticket with a realistic date, when it will be fixed (ETA)