Physics:
On GPS, 149Tb was collected during the nights from Mon-Fri and then send to PSI in the morning for pre-clinical trials of this isotope for targeted alpha therapy. During the days and in the weekend, VITO took over with 8Li beams to investigate diffusion of Li ion in solid state batteries interesting for electric cars etc. In parallel, also stable Ne and Xe beams from the EBIS were sent to Miniball for test of new detectors. Without major problems, all users were satisfied.
Targets:
Schedule:
- Quentin Vuillemin
- Next target change, PLC discussion
- Last 2 weeks of schedule:
- very tight with many important runs
- 08/12 as of 13h30: HT measurements for reference values (drain current) before IBDRS work (Boris tube integrity)
- Organise review of schedule: what to keep, what to improve, ... at end of the year: 16/12
- Length target change LIST
- EBIS replacement after end of HIE-ISOLDE