Service Cell preliminary design study - weekly meeting
Attendees W-04:
Jean-Louis, Gemma, Ahmad, Séraphin, Bruno, Gaëlle
Discussed subjects :
- Wrap-up date:
Unfortunately the first proposed date (01/19/2026) is not convenient anymore for BNF. We proposed instead 02/17/2026, CERN will confirm if this date is suitable.
- BNF answered to CERN feedback on the deliverables:
CERN will analyse our answers and come back to us within a week. Meanwhile, we do not update the deliverables yet.
- Functional Analysis update:
BNF will highlight the goal of the functional analysis in the report, that it serves as a reference for the current study and it shall stay frozen during the analysis.
- Steel cell VS Concrete cell:
BNF will add more details in the report about the non-viability of a steel cell in our current study, and about the benefit of a concrete cell (dimension, configuration, economics aspects etc).
- Cost study:
The cost analysis is on-going on BNF side. BNF will describe different administrative scenarios (subcontractor / companies organization) for the cell construction, our equipment’s scope and the limits of our installation capacities.
Next meeting will take place on Thursday 01/29/2026 at 2 PM.