Meeting Minutes
HL-LHC Common Meeting on Cryo Schedule
Date: 17 September 2025
1. Attendance
Present:
- Paolo Fessia
- Davide Bozzini
- Joao Carlos Batista Lopes
- Thomas Bauler
- Henry De Maynard
- Vanessa Gahier
- Emmanuel Monneret
- Michele Sisti
- Antonio Perin
- Markus Zerlauth
- Maria Perez Ornedo
2. QPLG Installation Schedule (Point 5)
- Emmanuel Monneret presented the proposed schedule for the installation of the QPLG, prepared with input from supplier Linde.
- The installation sequence was described and agreed, with key points as follows:
Planned Sequence
- Week 39: Start scaffolding installation in the US, up to the first support of the QPLG. First support to be delivered and temporarily stored on scaffolding.
- Supports availability: deliveries expected in Week 40.
- Weeks 40–41: Continue scaffolding installation in pit. Additional QPLG supports to be stored progressively on scaffolding.
- Guardrails, team availability and safety confirmed.
- Week 42: Parallel activity planned – continuation of scaffolding + modification of the top structure.
- Week 43: Planned parallel activity of installing supports in the pit + work on QPLG platform.
- Warning: co-activity not possible due to safety risks.
- Weeks 44–49: Installation of vertical lines.
- Action: Modus operandi to be provided by EN-HE and validated.
- Additional in-situ checks required (X-rays, leak tests). Planning to be refined accordingly.
- Week 51: Installation of the compensation box (critical element due to shape, location, and timing before Christmas).
- Risk flagged: activity may be risky unless properly planned and risks fully assessed.
- Compensation box handling:
- No solution currently available for EN HE transport team.
- If a specific lifting beam (palonnier) is required, with a lead time of 2–3 months.
- Preliminary document from Emmanuel indicates feasibility, but requires immediate submission to EN-HE for assessment.
- Action: Emmanuel Monneret to send technical information to Maria Perez Ornedo.
- Week 2 (2026): Completion of compensation box installation.
- Week 3 (2026): Line testing.
- Weeks 4–5 (2026): Scaffolding dismantling. Expected completion by Week 5.
- Dismantling foreseen to finish by Wednesday of Week 39; restart in Week 40.
- Action: starting date to be confirmed.
- Marking responsibility: Cryoworld.
- Week 5 (2026): Installation of upper shaft structure (cannot be done in parallel with pit activities).
3. Adjustments to Planning
- Ouvaroff intends to start works week 39.
- Henry De Maynard assessed the proposed schedule.
- Based on collected information:
- If scaffolding in the pit cannot start in Week 39 → earliest feasible start is Week 40.
- Risks linked to compensation box installation before Christmas require rescheduling.
- As a result, the full sequence is now planned to finish by end of February 2026 the latest.
4. Critical Path & Dependencies
- The sequence is critical for the HL-LHC project, as it impacts:
- Installation of the QURCG in US57.
- Installation of the QXL in UR55.
- To mitigate impacts on QXL installation:
- On 18/09/2025, six QXL elements will be stored in SD57.
- Later relocation: 2 elements → UR55 and 4 elements → US57.
- This allows QXL installation to proceed in parallel with QPLG.
- Note: Current understanding is that QXL elements cannot be lowered into the pit while QPLG scaffolding is in place. Study in progress to assess the feasibility.
- Action: Options to lower down QXL modules with shaft scaffolding in place will allow managing the co-activities and schedule between QPLG and QXL, and disentangle dependencies.
- EN-HE to provide feasibility studies and propose multiple options.
- A meeting (date to be defined rapidly) will be organized to assess risks and validate the chosen solution, with participation from WP9, HL-LHC project team, scaffolding team (BE-AA), and EROS representative.
- Note: The pit is expected to be available between Weeks 7–9 of 2026 for lowering QXL elements.
- Reduced co-activity at Point 5: UR must be freed by Weeks 22–23 of 2026 at the latest for patch panel installation.
5. Next Steps / Actions
- WP9 to provide EN-HE with a detailed installation sequence, including:
- Handling steps of the QPLG (lifting, welding, rotating, lowering).
- Special attention to handling procedure of the critical element compensator.
- Consideration of co-activity between pit and top-of-pit works (not allowed).
- EN-HE & Safety Coordinator to assess:
- Safety risks of compensation box installation.
- Overall modus operandi for vertical line installation.
- WP9: Refined planning to integrate mandatory checks (X-rays, leak tests) to optimize activities.
- WP9 and EN-HE: Confirmation needed whether QXL elements can be lowered with scaffolding in place.
- Feasibility study and multiple options to be presented on QXL lowering (see Section 4).
6. Risks & Warnings
- Parallel works in pit and on top structure are not deemed possible due to safety risks.
- Compensation box installation before Christmas is high risk; must be reassessed after further details are provided to EN-HE.
- Handling of compensator is critical – requires careful planning and risk mitigation.
- Effective communication of procedures is key for:
- Better understanding of the impact on planned activities.
- Assessing the consequences on the overall project schedule.
- Enabling validation of activities by the Safety Coordinator.
- In terms of administrative procedures (not discussed during the meeting but added to the minutes as a reminder), it is reminded that the Safety Coordinator must be fully aware of and validate the activities before they start (not discus.
- As an indication:
- the PPSPS shall be submitted 2 weeks the latest before the activity starts
- The VIC is carried out 1 week the latest before the activity starts
There are minutes attached to this event.