Common meeting on cryo schedule - QPLG and QXL installation schedule

→ Europe/Zurich
112/2-032 (CERN)

112/2-032

CERN

10
Show room on map

Meeting Minutes

HL-LHC Common Meeting on Cryo Schedule
Date: 17 September 2025


1. Attendance

Present:

  • Paolo Fessia
  • Davide Bozzini
  • Joao Carlos Batista Lopes
  • Thomas Bauler
  • Henry De Maynard
  • Vanessa Gahier
  • Emmanuel Monneret
  • Michele Sisti
  • Antonio Perin
  • Markus Zerlauth
  • Maria Perez Ornedo

2. QPLG Installation Schedule (Point 5)

  • Emmanuel Monneret presented the proposed schedule for the installation of the QPLG, prepared with input from supplier Linde.
  • The installation sequence was described and agreed, with key points as follows:

Planned Sequence

  • Week 39: Start scaffolding installation in the US, up to the first support of the QPLG. First support to be delivered and temporarily stored on scaffolding.
    • Supports availability: deliveries expected in Week 40.
  • Weeks 40–41: Continue scaffolding installation in pit. Additional QPLG supports to be stored progressively on scaffolding.
    • Guardrails, team availability and safety confirmed.
  • Week 42: Parallel activity planned – continuation of scaffolding + modification of the top structure.
  • Week 43: Planned parallel activity of installing supports in the pit + work on QPLG platform.
    • Warning: co-activity not possible due to safety risks.
  • Weeks 44–49: Installation of vertical lines.
    • Action: Modus operandi to be provided by EN-HE and validated.
    • Additional in-situ checks required (X-rays, leak tests). Planning to be refined accordingly.
  • Week 51: Installation of the compensation box (critical element due to shape, location, and timing before Christmas).
    • Risk flagged: activity may be risky unless properly planned and risks fully assessed.
    • Compensation box handling:
      • No solution currently available for EN HE transport team.
      • If a specific lifting beam (palonnier) is required, with a lead time of 2–3 months.
    • Preliminary document from Emmanuel indicates feasibility, but requires immediate submission to EN-HE for assessment.
      • Action: Emmanuel Monneret to send technical information to Maria Perez Ornedo.
  • Week 2 (2026): Completion of compensation box installation.
  • Week 3 (2026): Line testing.
  • Weeks 4–5 (2026): Scaffolding dismantling. Expected completion by Week 5.
    • Dismantling foreseen to finish by Wednesday of Week 39; restart in Week 40.
    • Action: starting date to be confirmed.
    • Marking responsibility: Cryoworld.
  • Week 5 (2026): Installation of upper shaft structure (cannot be done in parallel with pit activities).

3. Adjustments to Planning

  • Ouvaroff intends to start works week 39.
  • Henry De Maynard assessed the proposed schedule.
  • Based on collected information:
    • If scaffolding in the pit cannot start in Week 39 → earliest feasible start is Week 40.
    • Risks linked to compensation box installation before Christmas require rescheduling.
  • As a result, the full sequence is now planned to finish by end of February 2026 the latest.

4. Critical Path & Dependencies

  • The sequence is critical for the HL-LHC project, as it impacts:
    • Installation of the QURCG in US57.
    • Installation of the QXL in UR55.
  • To mitigate impacts on QXL installation:
    • On 18/09/2025, six QXL elements will be stored in SD57.
    • Later relocation: 2 elements → UR55 and 4 elements → US57.
    • This allows QXL installation to proceed in parallel with QPLG.
    • Note: Current understanding is that QXL elements cannot be lowered into the pit while QPLG scaffolding is in place. Study in progress to assess the feasibility.
  • Action: Options to lower down QXL modules with shaft scaffolding in place will allow managing the co-activities and schedule between QPLG and QXL, and disentangle dependencies.
    • EN-HE to provide feasibility studies and propose multiple options.
    • A meeting (date to be defined rapidly) will be organized to assess risks and validate the chosen solution, with participation from WP9, HL-LHC project team, scaffolding team (BE-AA), and EROS representative.
  • Note: The pit is expected to be available between Weeks 7–9 of 2026 for lowering QXL elements.
  • Reduced co-activity at Point 5: UR must be freed by Weeks 22–23 of 2026 at the latest for patch panel installation.

5. Next Steps / Actions

  1. WP9 to provide EN-HE with a detailed installation sequence, including:
    • Handling steps of the QPLG (lifting, welding, rotating, lowering).
    • Special attention to  handling procedure of the critical element compensator.
    • Consideration of co-activity between pit and top-of-pit works (not allowed).
  2. EN-HE & Safety Coordinator to assess:
    • Safety risks of compensation box installation.
    • Overall modus operandi for vertical line installation.
  3. WP9: Refined planning to integrate mandatory checks (X-rays, leak tests) to optimize activities.
  4. WP9 and EN-HE:  Confirmation needed whether QXL elements can be lowered with scaffolding in place.
    • Feasibility study and multiple options to be presented on QXL lowering (see Section 4).

6. Risks & Warnings

  • Parallel works in pit and on top structure are not deemed possible due to safety risks.
  • Compensation box installation before Christmas is high risk; must be reassessed after further details are provided to EN-HE.
  • Handling of compensator is critical – requires careful planning and risk mitigation.
  • Effective communication of procedures is key for:
    • Better understanding of the impact on planned activities.
    • Assessing the consequences on the overall project schedule.
    • Enabling validation of activities by the Safety Coordinator.
  • In terms of administrative procedures (not discussed during the meeting but added to the minutes as a reminder), it is reminded that the Safety Coordinator must be fully aware of and validate the activities before they start (not discus.
    • As an indication:
      • the PPSPS shall be submitted 2 weeks the latest before the activity starts
      • The VIC is carried out 1 week the latest before the activity starts     
There are minutes attached to this event. Show them.
The agenda of this meeting is empty