Status of BGI integration #5

Europe/Zurich

Integration

Vazquez and B. Riffaud to discuss:

    • TE-VSC requirement: maintain 300 mm gap between magnets.
    • Bellows will be defined.
    • Current system length is already 1 m longer than initial integration. Requirements discussed add approximately 600mm, making it an extra +1.6 m length from the original integration.
    • Discussion to be held to find solutions for reducing this length.

 

Vacuum & MDX Chambers

  • MDX opening discussion:
    • 123 mm opening: D. Boddart is testing this — The cost could be 5–10 k CHF × 8 units (total of up to 80kCHF).
    • 100 mm opening: smaller cost but requires machining of the opening, more resources & money.
    • Vacuum chambers: ~5 k CHF each, 3 per side, the costs would be similar for either configuration.
    • Preferred vacuum standard: DN100.

 

Next meeting actions: 

  • Chiara to discuss with Christelle next week (w/c 13th october).
  • B. Riffaud, C. Vazquez discussion pending on additional length feasibility.
  • ECR update to reflect changes once decisions confirmed.
There are minutes attached to this event. Show them.
    • 13:45 14:30
      BGI Integration review 45m

      Integration

      Vazquez and B. Riffaud to discuss:

        • TE-VSC requirement: maintain 300 mm gap between magnets.
        • Bellows will be defined.
        • Current system length is already 1 m longer than initial integration. Requirements discussed add approximately 600mm, making it an extra +1.6 m length from the original integration.
        • Discussion to be held to find solutions for reducing this length.

       

      Vacuum & MDX Chambers

      • MDX opening discussion:
        • 123 mm opening: D. Boddart is testing this — The cost could be 5–10 k CHF × 8 units (total of up to 80kCHF).
        • 100 mm opening: smaller cost but requires machining of the opening, more resources & money.
        • Vacuum chambers: ~5 k CHF each, 3 per side, the costs would be similar for either configuration.
        • Preferred vacuum standard: DN100.

       

      Next meeting actions: 

      • Chiara to discuss with Christelle next week (w/c 13th october).
      • B. Riffaud, C. Vazquez discussion pending on additional length feasibility.
      • ECR update to reflect changes once decisions confirmed.