CMS Gas Systems meeting

Europe/Zurich
20/1-004 (CERN)

20/1-004

CERN

15
Show room on map

RPC eonex preparare per 1 rack. Necessario spegnere un giorno prima. Poi si riparte venerdi' mattina

RPC high flow test in barrel (LS3)

RPC purif 3 electrilac modif -> CMS will do the work during LS3

Test per purif elec modif in atelier. Setup in atelier

 

FGR should we add a module? or should we test the distrillation? or parallel cooling? how to do?

Simulazione distillazione per mix R134a/CO2

 

isoltut per ghiaccio scambiatori FGR da chiamare -> Andrea

 

CF4 alarm/ warning to be completed/in progress. Qualcosa c'è!

 

CF4 compressor alternative to small RIX  

 

N2 flow alarm -> something to be done

 