R2E calculations for HI-ECN3 (SHiP CCC in TCC8)
zoom
CERN
Participants:
BI: Gunn, Mark, James, David Gancarcik
R2E: Dominika, Luigi
WP2: Lawrence, Francesco (Matthew excused)
1. Purpose
-
Define location and integration constraints for the CCC in the SHiP beamline (WP2).
-
Review radiation conditions and mitigation options for CCC electronics (R2E).
2. WP2 Discussion — CCC Location & Integration
Location
-
Proposed installation: between two quadrupoles, ~20–25 m apart.
-
Longitudinal position: 130–140 m upstream of SHiP target, upstream of dilution system.
-
Area has ample space and stable magnetic environment.
Beam Pipe & Geometry
-
Acceptable aperture: 80–159 mm → all GSI CCC designs (DN100, DN150) compatible.
-
No beam impedance concerns (straight transfer line).
Height & Access
-
Future SHiP beamline will be placed higher than current line → WP2 to provide:
-
Beam pipe height
-
Ceiling clearance for cryostat + fill port
-
Cryogenic Services
-
Location is underground, access only via lift → issue for 500 L LHe dewars.
-
Must check with HSE if LHe transport is allowed.
-
Additional service needs: electrical power, cooling water, compressor location, routing of lines.
Action Items (WP2 / BI)
-
WP2: provide beam height + hall clearance (Bea). - ONGOING
-
BI: obtain STEP file of GSI prototype CCC and send to Beatrice for integration study. - DONE
-
BI: request visit to bldg. 912 (contact: Bastian Rae).- ONGOING (check with RP (@Yann Pierre Pira) for the best time)
-
BI: consult HSE about LHe dewar transport. - ONGOING
3. R2E Discussion — Radiation Environment
Existing Data
-
No simulation at 130–140 m.
-
At 30 m upstream: ~100 Gy/year, mainly from the backscatter radiation from target
Expected at CCC Location
-
Backscatter expected to decrease strongly (1/r²).
-
Main contribution will be gas–beam interaction cone.
Vacuum Issue
-
Beamline vacuum: 10⁻³ mbar → relatively high radiation from residual gas.
-
WP2: cannot improve significantly due to cost and long beamline.
-
Differential pumping only partially feasible.
Possible Mitigations
-
Iron shielding upstream of CCC → WP2 confirms feasible.
-
Explore local vacuum improvement, but adds cost.
-
Evaluate routing sensitive electronics away from beam axis when possible.
4. Electronics Radiation Testing
-
MAGNICON SQUID electronics are not radiation-hard.
-
AD-CCC has low radiation but one recent failure (unknown cause).
-
BI will perform dosimetry in AD in 2026 (Mark).
-
R2E will run new FLUKA simulations at actual CCC location.
-
CHARM radiation testing is possible (higher dose than SHiP).
Action Items
-
BI: send AD-CCC location to R2E. (element name is DR.CCC1501 in AD ring, vacuum sector 2A) - DONE
-
R2E: perform new FLUKA simulation + search for past radiation data in AD. - ONGOING
-
BI: install dosimeters in AD in 2026. (Mark) - ONGOING
5. Key Open Points
-
Helium access: Can 500 L dewars be transported underground via lift? (HSE check)
-
Height limits: Need beam pipe and hall clearance to confirm cryostat design.
-
Radiation environment: Dependent on updated simulations and shielding strategy.
-
Vacuum constraints: Residual gas interactions are likely the main source of radiation.
6. Conclusion
-
The location between the quadrupoles is suitable and beam-pipe compatible.
-
Major concerns remain: cryogenic accessibility, radiation dose, and height limitations.
-
BI, WP2, and R2E will continue with integration, simulation, and safety studies.
Update: 11 Dec 2025 (questions from Matt Frazer):
-
Where is this location? TCC8 or TDC85?
-
stable magnetic environment -> magnetic environment to be quantified
-
I will add a statement on “Magnetic Environment" in the FS including the pulse shape of the beamline magnets (most will be static during the spill and ramping at ~ 1% level) but the dilution magnets will be oscillating and swinging the polarity of the B-field (something to keep in mind)
-
The access conditions between TCC8 and TDC85 are very different, with the later requiring also a beam stop of EHN2 for access.
-
Suggest we do the studies first before jumping into mitigation options: the dose has to be low for SHiP in any case.
-
We can check the radiation dose today on the beam line from the MCWG summary and Daniel Soderstrom’s talk (passive DOFRS and BLMs) to give us a feeling (even though we expect to bring down the beam loss levels in the future)