New trip to CINEL planned this Wednesday to assess the jaw assembly and testing activities. Important phase of the production.
Thibaut and Francesco are managing a new shipment to CINEL (3 SB bellows, 1 SB IPN, BPM components, RF rails?).
Ongoing important activities (among others) are:
-> Testing Staubli locking system;
-> Converging on water cooling system (We need the head loads calculation from staubli to staubli including both jaws and tanks circuits;
-> Testing the spreader beam proposed by CEM for robotic compliance;
-> Preparation of 20 collimators removal from machine;
-> Movement of our stock to building 263 when available.
Production of ~25 new collimators is not acceptable at this stage. One shall find a solution to prevent operational failures post LS3.
11:20
→
11:35
Coordination of activities15m
Update on timeline for definitive copper drift tube for TCTPXVs (Gregory Cattenoz or Julien Finelle)
11:35
→
11:45
Update from Project Steering Meeting (PSM)10m
Let's go through the slides presented.
Speaker:
Francois-Xavier Nuiry(CERN)
11:45
→
11:50
Update on preparations for collimator activities in the summer5m