ADTC meeting
AD LS3 planning
Francois Presented the planning for services disruptions and the next major activities, concerning sector 3 magnets extraction (detailed in Joris’ talk).
The upcoming facility disruptions were detailed, including the relocation of the small pump from December 1st to January 15th which will affect demineralized water availability, and HVAC refurbishment work between March 3rd and September 10th that will impact smoke extraction systems. Concerning this point, it was confirmed by HSE that in case of fire permit, a thorough assessment will be required to determine compensation measures. Francois indicated that annual AUG testing date is not confirmed yet. ELENA operations are extended to November 30th and will transition to maintenance work starting December 1st. Alexandre explained that they use a shared consignment form for all line items. ZQNAs (first batch of 3) vacuum acceptance tests planned for the last two weeks of December remains to be confirmed.
Magnets extraction for refurbishment in sector 3
Joris showed the ongoing activities for the extraction of 5 magnets in sector 3 for refurbishment. The work is now complete, with only safety guardrails remaining to be put in place. The ALPHA cabin will stay in its current location, and will be re-installed only after asbestos / lead check and after magnets are re-installed in position.
LS3 Shutdown Experimental Plans
BASE: Barbara showed the status of the ongoing measurements at BASE. The precision measurements are expected to run through the entire 2 years of YETS, first with pbars, then with protons. Due to the sensitivity of the magnetic fields fluctuations, the usage of crane is required to be limited to the Monday, Wednesday and Friday 8 -14h only as much as possible.
BASE will rely on lHe/LN2 delivery to be continued as normal (1 lHe dewar per week).
ALPHA: Adam showed the expected activities during LS3, which include several major improvements with phase of operation with protons and hydrogen atoms. To this aim, services are expected to be operational as much as possible, within the planned disruptions indicated. Francois indicated that some short compressed air disruptions are to be expected linked to the HVAC/demi water consolidation works. These can be accommodated if they are announced in advance.
AOB
The analysis of the AD optics survey is ongoing and the outcome and proposals will be discussed in one the next ADTC meetings.