ER.BTV12 Upgrade discussion
Jose, Ben, Alexandre, Theo, Chris, me
- Slides explaining reasons for upgrade and new design (Stephane)
- NEG can be activated only a certain number of times (~15) --> important to optimize number of openings
- Check what could be improved in the sector also (ask BI colleagues) since it will be open
- Push pull below less for the new BTV would be used (as for ELENA)
- Firing of the push pull required
- Check if EI.BTV10 and 20 could be replaced as well at the same time
- Easier for VSC if we keep vacuum chamber (no new ones)
- we will ask MME if they can go through as well
- General agreement to do the upgrade of the ER.BTV12 (at least) during LS3
- Planning
- Commissioning LEIR is April 2028
- Detail planning not known so far --> Wait until it becomes a bit more realistic
- Potentially, BTV replacement in Q4 2027 or Q1 2028
- Summary of actions:
- Continue the ER.BTV12 design as 1st priority (BI/MME)
- ECR will be finalized ASAP (BI)
- Check the EI.BTV10 & 20 consolidation feasibility at the same time (BI/MME)
- Check planning with VSC once available and rediscuss together the installation plan (VSC/BI)
Stephane