- Cables
- For suspending the cables SCE has said they can easily attach them onto the scaffolding - however, this would mean they would still require suspension for 1 week as the time it takes to detach the cables, then build scaffolding, then attach cables to scaffolding this would be the estimated lead time.
- A new on-site visit will be requested in order to see if a temporary frame can be built over the beamline in order to rest the cables on that, but there is limited space
- If possible / space allows, mechanical protection over the beamline is preferabe as this would then protect even from the construction of the scaffolding itself
- Protection of equipment
- The idea is this will now be done by RBS. Timeline still TBD.
- Working footprint attached
- This shows the area that will be worked on taking into account both the dismantling as well as the construction phases
- GPS exhaust vac pipes
- Re-routing not possible
- plan b - will design a permanent shielded box
- Dismantling
- CV
- require 2 weeks
- space for 2 pallets for dismantling of AC units and ducts
- Route for removal of pallets?
- ACE
- 3 weeks end of may/ early june
- green cage and light structure
- Route to be defined and location of pallets to be defined
- Integration
- Meeting tomorrow afternoon for revision of current integration
- Planning
- Carlotta to come up with a master plan which integrates all groups on a weekly block schedule
- This can then be circulated among relevant groups by management
- ECR for EP cage change?