RILIS coordination meeting 1

Europe/Zurich
    • 09:00 09:05
      Introduction 5m
      Speakers: Katerina Chrysalidis (CERN), Laura Lambert (CERN)
    • 09:05 09:10
      SY-STI 5m

      Week 9:

      • Clearing of hall space for removal works
      Speakers: Jordan Ray Reilly (The University of Manchester (GB)), Katerina Chrysalidis (CERN)
      • Still some cables below GLM that still need to be rmeoved
      • Dye prep cupboard and dye circulators need removing (special intervention required - who is organising this?)
      • All equip other than profiles to be removed by the end of this week
      • Emptying of the sas by the end of this week
      • To order some pallets for requip removal
    • 09:10 09:20
      EN-CV / HE 10m

      Week 9:

      • Pipe removal below barrack update
      • Equipment removal on roof - preparation of worksite (cc HE)

      Week 10:

      • Equipment removal on roof with EN-HE
      Speakers: Nina Marianna Szczepanik-Scislo (CERN), Xavier Decrand (CERN), Yann Denis Robert Seraphin (CERN)
      • EN-EL to disconnect electrical power supply
        • Xavier to follow up with Andy directly
      • No news on quotation - means no news on equipment dismantling on roof
        • Hopefully start next mon
        • Require 2 weeks total. Likely 1 week should be sufficient
      • Start with preparation of roof tomorrow
      • Xavier to order his own pallets to place equipment
      • Pipes below RILIS finished last week
    • 09:20 09:35
      EN-EL 15m

      Week 9

      • Decabling inside laser lab
      • Survey, primarily below bunker
      • IT decabling (25.02 - 26.02)

      Week 10

      • Decabling / suspension around GLM/GHM area as well as in and around green cage (05.03 - 06.03)
      Speakers: Andy Jose Nicolas Hamy (CERN), Jose Ramon Rendon Molina (CERN), Rustan Calming, Samuel Pierre Fasel (CERN)
      • Just waiting on green light for the survey
      • After the survey is done, we need to validate cables to be removed, and then decabling and suspension can proceed
      • Start survey tomorrow (providing contractors have the manpower)
        • Technical visit planned for this afternoon with contractor
        • Either Laura or someone else from the RILIS team to be present during the survey for efficiency and validations
      • Week 11 - decabling and suspension starts
    • 09:35 09:45
      RBS 10m

      Week 9

      • Various equipment removal (patch panel, teslameters, tape stn electrical rack)
      • Disconnected gas line from STI removal
      • Frame around beamlines

      Week 10

      • Dust protection layer
      Speakers: Laura Lambert (CERN), Oscar Fjeld (CERN)
    • 09:45 09:50
      Integration 5m

      Week 9

      • HRS door
      • conflict identification with services between IS-COOL and GPS bunker
      Speaker: Vincent Barozier
      • Cabinet from BI this is conflicting with a primary beam of the platform
      • Samuel to ask Jean-Pierre if he's done any integrations of this area
      • Vincent to come on site wed morning to finalise integrations
        • Tiago to join after 10am
        • Laura/Kati to join for part of it in order to ensure all equipment is taken into account
    • 09:50 10:00
      AOB 10m
      • Green cage final inventory this wed