RILIS Coordination Meeting 3

Europe/Zurich
    • 09:00 09:05
      SY-STI 5m

      Week 11:

      • Displacement of patch panel
      • Plastic dust protection installed over beamline and various equipment
      Speakers: Jordan Ray Reilly (The University of Manchester (GB)), Laura Lambert (CERN), Oscar Fjeld (CERN)
      • Displacement of patch panel might have to be shifted to next week
      • Re-design of cable suspension frame infront of HRS door this week a priority
    • 09:05 09:15
      EN-CV / HE 10m

      Week 11:

      • Equipment removal on roof

      Week 12:

      • Compressed air line re-routing?
      Speakers: Nina Marianna Szczepanik-Scislo (CERN), Xavier Decrand (CERN), Yann Denis Robert Seraphin (CERN)
    • 09:15 09:25
      EN-EL 10m

      Week 11:

      • Decabling / suspension below barrack and inside lab
      • small cable trays and cables supporting communication wiring at GHM to be removed - Guilherme March 10th
      • Rack next to ISCOOL cage, craned out mon or tues - Julien

      Week 12:

      • Re-routing / suspension of cables on roof
      Speakers: Andy Jose Nicolas Hamy (CERN), Joao Martins Correia (Universidade de Lisboa (PT)), Jose Ramon Rendon Molina (CERN), Julien Parra-Lopez (CERN), Nenad Simic (CERN), Rustan Calming, Samuel Pierre Fasel (CERN)
    • 09:25 09:30
      Integration 5m

      Week 11:

      • Integrate solution for conflicting primary beam with BI rack
      • Integrate cross beams into new lcoations
      • Include integrations from EN-EL
      Speakers: Clement Morselli, Jean-Pierre Billon-Grand (CERN), Tiago Nico (CERN), Vincent Barozier
      • New platform, cross beams relocation and shifting of primary beam to be integrated next week
        • Tues or wed latest for 3D model to be finalised by SCE
    • 09:30 09:35
      AOB 5m
      • RP monitor on roof of RILIS recommended removal to avoid damage during works
      • Pb removal
        • Confirm mask training complete
        • Coordinate lead contamination test
        • If mask training not done on time, can see with doing the work in cagoules instead