1. RFD-SPS restarted for the last year of operation, RF conditioning ongoing. 4 MDs (2 in April, Jun 29, Jul 8)
2. 3 cold tests performed on RFD 1/3 after light BCP at CERN. Cavities are stuck at medium field multipacting barrier between 1.5- 2MV
3. Jacketing of the CERN-RFD3 finished, RFD4 sub-components read, frequency trimming expected in a few weeks
4. Visit to Zanon two weeks ago for brazed flange inspection - inspection report: EDMS 3428524
5. Visual and UT Inspection of RFD1 flanges agreed with AUP, we will evaulate if RFD3 needs an inspection as well
6. UK2 collaboration agreement update ongoing with input from Nik et al., will finalize it in coming weeks.
7. PRR with TRIUMF successfully completed with recommedations being followed up and June follow-up meeting - EDMS 3405316