- First order for coil components and winding/reaction tooling (launched in October 2025): Some exchanges with the Indian company, delivery for mid / end of March
- There is a second order placed in Portugal, which includes the impregnation mold and part of the lifting tooling: For this one the delivery is expected by May (6-8 weeks)
- Concerning the Mechanical structure: DR request launched and budget lies in "no market survey" range. Reduced time procurement expected. We should have the components in-house by end of June.
- Al-shells are already in-house. MME is aware
- The components for the winding of the Cu coil will be available before summer holidays. This will be the first winding.
- The objective is to have two Nb3Sn coils before the end of the year