EPC platform:
- advancing well. Interconnecting HT cables racks/patch panels being installed
- mis-match cabling data base and destination for a few cables to be solved (Simon / Nicolas / Rustan)
- 12 new HT cables for CAO switching will be routed via LA1 cable trays: re-inforcement to be put in place (1 extra pillar IPN 30cm bracket): Budget Code?
- old blue racks will be dismounted soon Last old blue rack will need to stay in place since it holds the vertical cable tray. New pillar(s) will be put in place to support the cable tray.
- alu 90 bracket on the 197 wall under the newely installed vertical cable trays to be removed (Oscar?)
HIE ISOLDE:
preparations CM1 dismount:
- request to remove/arrange shielding blocks around cryo openings roof gone out: To be done this week (transport Yann Seraphin). Small black plastic palette in place. Attn. keep concrete roof plates to be removed for CM1 transport free.
- survey CM1, XLN2 and XLN3 intertank sectors position verification Wedn-morning 04/03 (Alexandre Beynel)
- survey BCAM (MATHILDE system) dismount Monday-morning 09/03 (Alexandre Beynel, Antje Behrens)
- request VSC (Guillermo Merino Fernandez) to start with vacuum dismounting work this week to reduce workload wk13 (23-25 March): Will be scheduled around survey work
- installation view ports CM1 around/after survey work (Mathieu Therasse)
HIE ISOLDE
BI preparations:
- move wooden box 'BI DBox' down from tunnel roof to between XT01/02: preparation DBox calibration work and CM1 XLN02/03 intertank units dismount (storage) (BI team, transport). To be done this week (transport Yann Seraphin)
Fibre optics in the hall:
- various fibres to be pulled (Benjamin Ninet / Nenad Simic):
FEC RC6 - OK can be done from the already installed connection box on the HIE tunnel wall - attn. not during CM1 transport/dismount
Fibre removal RILIS and ISCOOL with RILIS works (Lukas Nies)
New fibres FEC's and White Rabbit (WR) deployment: New fibres asap in cable tray on the 170 Saleve wall (before RILIS dismount). Connection box next to REX RF room entrance (high up). Postponed interconnections from the (new) fibre box to CAO, RILIS and ISCOOL FEC's after RILIS refurbishment