ISOLDE Technical Coordination Meeting (LS3)

Europe/Zurich
508/1-001 (CERN)

508/1-001

CERN

20
Show room on map
Zoom Meeting ID
62093336977
Host
Joachim Vollaire
Useful links
Join via phone
Zoom URL
    • 14:00 14:05
      General news - Review of minutes 5m
      Speakers: Erwin Siesling (CERN), Joachim Vollaire (CERN)
    • 14:05 14:15
      Safety matters 10m
    • 14:15 14:20
      IBDRS project - activities update 5m

      EXcavation ongoing
      Preparatory activities for niche (camera implementation). Work procedure will need to be adapted due to ALARA constraints....
      BTY line- issue with handling- being discussed with TE-MSC.

      Speakers: Ana-Paula Bernardes (CERN), Joachim Vollaire (CERN)
    • 14:20 14:25
      Ventilation primary areas upgrade 5m
      Speakers: Joachim Vollaire (CERN), Melania Averna (CERN)
    • 14:25 14:30
      RILIS Laboratory upgrade project - activities update 5m
      Speakers: Carlotta Porzio (CERN), Katerina Chrysalidis (CERN), Laura Lambert (CERN), Sebastian Rothe (CERN)
      • STI
        • Tape station rack removed and temporary stored down the hall (see photo)
        • Frame built by Oscar by HRS for cables - this needs to be redeisgned / discussed to maintain access for HRS
          • Options:
            • Remove HRS door completely and include lock for secondary door (lock to be available to RP, firefighters, and traka)
            • Temporarily place cables on frame, once scaffolding built, transfer cables so they are suspended from scaffolding and dissassemble frame 
        • Dust protective plastic layer to be put up next monday
        • Equipment on hall floor removed last week - space now available for large equipment removal
        • Gas lines in ISCOOL removal next week
        • Chemicals from dye prep cupboard being organised this week for storage elsewhere
      • EN/EL - IT
        • Survey finalised yesterday - contractors did not perform satisfactory job, so Laura/ Rustan finished up yesterday
          • Decabling and suspension planned to start next week
          • Roof cables suspension week 12
        • IT cables removed
        • Fiber optic
          • confirmed OK to shift cable on roof providing they are present during re-positioning
            • Follow up technical visit for back up plan incase of damage to cables
          • Fiber cable to ISCOOL cage to be removed by Lukas with supervision from EN/EL next week
      • Integration
        • HRS door
          • Meeting planned March 11th with Didier for new design
          • Replacement timeline still TBC
        • New rack to be placed in newly available space from HRS door replacement
          • This (tbc) will house the 2x teslameters and tape stn fec
        • RILIS room layout being finalised -> adapted height of entry with shielding towards GLM -> this will not be removable (as foreseen before)
      • CV
        • Confirmed roof equip removal starting mon - crane will be required!
        • Pipes inside lab (all but one connected to water) removed yesterday - thanks Francisco!
        • Technical visit for displacing compressed air line yesterday - inspection for work required ongoing this week
      • Safety
        • Found more lead to be removed inside wall toward HRS separator, this will be included with the Pb removal campagn for RILIS (see photo)
          • As well there has been some lead found in an ancient radioactive sample box in the back corner or the old control room, this will also be added to the RILIS "pile" (see photo)
        • Crane access above SSP area (placement of shielding during experiments) with new RILIS design, confirmed OK with crane support
      • Planning
        • Weekly coordination meeting between groups involved every monday at 9am - Please contact Laura/Kati if you have not had an invite but would like to attend
    • 14:45 14:50
      AOBs 5m
    • 14:50 14:55
      Planned visits 5m
      Speaker: Hanne Heylen (CERN)
      • Proposal to limit visit on Friday next week to low E area.

       

      List for the upcoming month: