HL-LHC Integration Meeting – Minutes
Date: 13 March 2026
Topics: LSS1/5 installation drawings, HL-LHC tunnel tracing for LS3, integration of dump ancillaries.
Actions
- Luca Gentini to upload on the Indico page an Excel list of all LSS1/LSS5 installation drawings for verification by equipment owners.
- Eric Page to provide naming corrections for the drawings by end of March 2026.
- Joao de Oliveira and Ricardo to perform Check 2, comparing beam points in the drawings with the Layout Database.
- BE-GM to perform a global check of the drawings to verify all tracing data is implemented.
- Equipment owners to perform the final validation of drawings and provide a digital signature for traceability.
- Luca Gentini to investigate the PLM solution for drawing validation while preserving the link with the 3D models.
- BE-GM to prepare and distribute an Excel template with tracing points for non-beam elements.
- Equipment owners to provide equipment models requiring tracing to Stéphane Maridor.
- Stéphane Maridor to compile tracing data, determine CSS coordinates, and upload Excel files in EDMS (one per LSS) for approval.
- Equipment owners to validate the final tracing point lists of non-beam elements in EDMS.
Findings
LSS1 / LSS5 Installation Drawings (Luca Gentini)
- The installation drawings are nearly finalized, with only a few updates remaining:
- Integration of the latest DCM and DFX models.
- Integration of the latest BPTQR model.
- Implementation of naming corrections from Eric Page.
- A three-step validation process will be applied:
- Check 1: internal verification by Luca Gentini.
- Check 2: comparison of beam points with the Layout Database by Joao de Oliveira and Ricardo, with a global review by BE-GM.
- Check 3: final verification and digital approval by equipment owners.
- For traceability of equipment owner validation, Luca is exploring three possible solutions (priority order):
- PLM validation of drawings without requiring approval of the associated 3D models, maintaining a permanent link between models and drawings.
- Creation of a dedicated 3D model container used only for drawing approval.
- Approval of PDF drawings in EDMS.
HL-LHC Tunnel Tracing for LS3 (Anna-Sarah)
- Anna-Sarah presented the status of tunnel tracing preparation for HL-LHC during LS3.
- The key milestone is the validation of tracing points by equipment owners by June 2026 for both beam and non-beam elements.
- Equipment owners are encouraged to anticipate their checks to ensure this deadline is met.
Process for Non-Beam Elements
- BE-GM will distribute an Excel template with tracing point names for validation.
- Equipment owners will provide equipment models to Stéphane Maridor.
- The integration team (Stephane Maridor) will:
- Compile the data from all equipment owners,
- Project the points to the tunnel floor,
- Determine coordinates with respect to the CSS reference system.
- The consolidated data will be uploaded to EDMS for final approval by equipment owners (one Excel file per LSS).
Integration of Dump Ancillaries
- Integration models for the HL-LHC dumps (UD62 and UD68) have been reviewed and integration uncertainties addressed.
- Model references were shared with ACE.
- Support cradles are in detailed design; completion expected by summer, with delivery planned for Q1 2027.
- Top ducts design is progressing to the detailed phase; final details (flexible supports, anchoring, connections to cooling ducts) will be defined after site visits and measurements at the start of LS3.
- The argon tank contract for detailed design, construction, and validation is about to be placed; the final design will be shared for review around July.