CMS Gas System Status meeting
-CMS gas coordinator is Michele Bianco
-who was asking ME0 by 2026? -> Maria Cristina/Andrea to check
-filters for endcap distribution racks ->layout and time for interventions to be discussed with CMS integration office -> TICKET to Andrea
-can we optimize stop of RPC by sincronizing the activities on one rack (safety valve, input regulation valve, filter, other) -> TICKET Andrea
-CMS will update the global schedule in May. To get feedback for LS3 asap after this update -> TICKET Andrea Maria Cristina CMS gas coordinator to update also our planning
-meeting with CMS gas coordinator, Pablo, ... before May -> TICKET Andrea Maria Cristina
-check and update the new infrastructure constrains for CMS and share -> TICKET CMS gas coordinator
-work package for new input regulation valve for RPC. who is paying what? -> TICKET
-email from David about RE: IT-5037/BE :LS3 LHC experiments gas supply infrastructure consolidation -->Preliminary schedule (4/3/2026) -> check if we have a ticket -> Andrea Maria Cristina
-same time in 2028 CF4 will be used by CSC and therefore CF4 recuperation operational -> TICKET and update LS3 planning