ISOLDE Technical Coordination Meeting (LS3)

Europe/Zurich
508/1-001 (CERN)

508/1-001

CERN

20
Show room on map
Zoom Meeting ID
62093336977
Host
Joachim Vollaire
Useful links
Join via phone
Zoom URL
    • 14:00 14:05
    • 14:05 14:15
      Safety matters 10m
    • 14:15 14:20
      IBDRS project - activities update 5m
      Speakers: Ana-Paula Bernardes (CERN), Joachim Vollaire (CERN)

      On behalf of the project: 

      Past week:

      • Continued with excavation of non-radioactive soil evacuation (working in the area between B. 198 and B. 170
      • Pre-construction of the niche for the GPS camera finalized.
      • Intallation of liner in the storage pit
      • Sprinckler system installation (dust management). 
      • Covering of GPS/HRS radioactive soil areas
      • Testings cleaning procedure for excavation machines
      • Cleaning of shielding blocks on top of the GPS dump before handling

      This Week:

      • Core drilling for the camera niche
      • Radioactive soil removal to reach the level 440.5 m.
      • Cleaning of blocks in dedicated tent (tests)
      • Handling of blocks on top of the GPS dump
    • 14:20 14:25
      Ventilation primary areas upgrade 5m
      Speakers: Joachim Vollaire (CERN), Melania Averna (CERN)
      • Outside work for pipe/duct work for EN-CV finalized (insulation in place)
      • Until mid-April, SCE-SAM will build the lateral protection wall for the ducts and prepare the area for the final shielding construction (needed for stray radiations) which will be included in the IBDRS phase 2 project.
      • Ongoing work inside Build. 197
      • Commissioning and reception of the new ventilation system expected Week 17
      • 20/03 craning planned for equipment delivery
      • Will communicate the date for the re-connection of the turnstile for access (requested to be done during the coming week).
    • 14:25 14:30
      RILIS Laboratory upgrade project - activities update 5m
      Speakers: Carlotta Porzio (CERN), Katerina Chrysalidis (CERN), Laura Lambert (CERN), Sebastian Rothe (CERN)
      • STI
        • Dust protective plastic layer has started being installed - SSP area priority
        • Patch panel has been shifted, a new frame will be built to secure it in place more than just zipties
          • If people like this new more accessible location, we could consider keeping it there in the long term
        • Clean up of roof either this coming Friday or Monday
        • New frame to be built by HRS door to hold cables, this will not obstruct the opening to the separator area
          • HRS door has been removed and the same lock cylinder has been taken from this door and placed in the second door through the chicane - so the key for access remains the same
        • Preparation and removal of lead hopefully next week
      • EN/EL
        • Decabling and suspension has finished below the barrack (minus a few cables through the I-beam which we will hopefully remove when dismantling via some screws)
        • Cable on roof to be shifted from wed-fri this week
        • Antenna on roof is dismantled
      • Integration
        • SCE contribution including new platform design, cross-beam shifted to new position, and re-positioning of primary beam next to BI rack to be updated with 3D model to be done today/tomorrow latest
      • CV
        • Roof equip. removal finished
        • Final pipe removal for inside the lab technical visit today
        • Compressed air line
          • Needs to be replaced by flexible line due to access restrictions
          • Cannot find isolating valve, therefore will need to cut compressed air to the entire hall
          • Timeline  - before end of April
      • SCE / ACE / HE
        • Opening of roof hatch 24.03
        • Tables inside RILIS to be removed next week
        • maybe starting to move some shielding blocks between RILIS and GLM starting next week - TBC
        • Shifting dismantling of green cage forward, this will now start week 14
        • Scaffolding around SSP area will go up the week before in week 13
      • Safety
        • Project safety meeting last week with new light on some requirements towards fire safety of beams
        • RP monitor on roof of RILIS being removed as we speak (helmet on)
        • Fire detection system removed last week
          • The pipe from the fire detection system was cut by another group prior to dismantling - equipment tampering, EN/AA to decide how to proceed
      • Planning
        • Weekly coordination meeting between groups involved every monday at 9am - Please contact Laura/Kati if you have not had an invite but would like to attend
    • 14:45 14:50
      AOBs 5m

      HRS field control and measurement:

      • Request from Marco Buzio TE/MSC to  house a full 19" rack. Proposal in x-entrance 170 R-020 with cables trhough existing hole (if fits with Ar/N2 and AC tubes). Would require to move the two spare-parts EPC cupboards elsewhere. Discussed with Vincent Barozier. To be discussed at the ICL.

      Separator Areas

      • Acces planned tomorrow 18/03 for 3D and equipment removal to prepare future core drilling (new survey lines)

      Target Area and BTY line work

      • Section of the BTY line vacuum pipe in Front of the GPS Faraday cage will be removed by TE-MSC on Thursday (needed for shielding installation)
      • Work preparation ongoing for BTY line disamantling. BHZ magnets don't fit through the current shielding door opening. Need to cut 10 cm of wall in the corner. 
      • Meeting next week: BTY Power converters consolidation - Work in Building 197. Review ECR and plan the work.
    • 14:50 14:55
      Planned visits 5m
      Speaker: Hanne Heylen (CERN)