Platform EPC:
- AC cabling and distribution finished: As built to be verified with the existing CATIA model in the frame of the zonage of the overhead crane.
- HT cables all reconnected and tests of the cables between patch panels and machine ongoing: Meeting held with WSS (Rustan Calming), contractor and RP (Nadine) on access to the separator zones. Cables numbering will be renewed / added.
- Support old/excisting vertical cable tray in place. Apart from the removal of the scaffolding the floor is ready for adaptation of the old false floor. Proposal Jean-Pierre Billon-Grand.
Fiber installation work:
- fiber duct installation along the Saleve wall and above RILIS barrack and GPS bunker has been done (31 March Nenad Simic & contractor) in coordination with green cage removal.
REX/HIE ISOLDE preparations CM1 transport:
- CM1 radiological aspects: List of isotopes with long live daughters were identified (Fabio). Data on duration, intensities and (estimated losses) has been compiled (Miguel). BAsed on the nuclide inventory provided by Fabio the transport will be exempted. To confirm this 2 last points of info are to be transmitted to Philippe Bertreix: - dose rate at contact (to be measured when CM1 is out of the tunnel), - confirmation there is no contamination accessible (RP, Erwin)
Info tunnel roof opening & transport CM1 -> SM18:
- PR214 verification done. Confirmation that the PUMA modification on the overhead crane PR214 will not hamper the handling of CM1. We will proceed with the schedule as planned.
The modification/displacement of the PUMA drum and cupboard will be carried out after the CM1 handling and transport, as of Friday 24th April. Verification proposed change before with integration (point for the ICL, Filippo Cappaletti, Vincent Barozier). Laser tables removal in week 18, after modification/removal PUMA drum, etc. (29/30 April).
- This Week 16 (13-17 April):
Tunnel has been opened Monday 13/04 (ahead of schedule - due to transport availability). (Thanks to the VITO team and others for clearing the Jura side HIE ISOLDE wall). Door to the tunnel roof closed by key (RF room) no access apart from HE/Tranport team.
CM1 out of tunnel to the handling zone Thursday 16/04 - Attention: craning work and handling equipment in the hall.
CM1 will be standing from 16 - 23 April in the handling zone next to the yellow RP buffer zone: vibration and inclination sensors + wrapping for transport
- Week 17 (20- 24 April):
Transport CM1 from ISOLDE 170 to SM18 - special transport (truck & trailer) arriving 23 April (confirmed). Heavy use of the overhead crane during handling in the 170 hall (CM1 onto pendulum/trailer).
SAS and handling zone to be empty (users will be informed). Parking to be empty (IBDRS project has been informed)
- Thursday 23rd April difficult traffic circulation around ISOLDE with the Rte Einstein closed (CM1 transport) and Rte Democrite closed (crane). Exeptionally Rte Rutherford will be opened - tbc with the 133 refurbishment project.
Perturbations to be expected end of the morning at the border when the road will be closed for ~1 hr to pass with the truck.
- RILIS planning kept in the loop (Carlotta, Laura), ISOLTRAP planning kept in the loop (Arthur Jaries) - ISOLTRAP dewars craning: mornings of Fri 17/04 (LN2), We 22/04 (LHe) and Fri 24/04 (LN2) in line with the CM1 handling planning.
Planning REX/HIE: 170 REX HIE planning | Document 3383102 (v.1)
Vacuum pumping / ventilation:
- For the investigation at EBIS to find an assumed leak its vacuum system will need to be restarted (Guillermo): Ventilation systems operational as of 27th April confirmed (requirement for the restart of the primary pumps)
Work in he 170 HT room:
- Julien Parra-Lopez: Replacement of the GPS and HRS target heating power supplies. New equipment has been moved up to HT room and installation is ongoing.
Beamlines:
- RC6 EN/EL AC cabling work has finished now follwed by signal cabling. The contractors have been informed and are aware of the CM1 tunnel opening and handling works and they will adapt accordingly.
HRS field control and measurement:
- Request from Marco Buzio TE/MSC to house a full 19" rack. Keep proposed position in 170 R-020 with cables through existing passage (if fits with Ar/N2 and AC tubes). Discuss and validate at the ICL meeting (16/04).