  • electrical cabinet and pipe (?) to be removed
  • follow up on shielding blocks to be ordered
There are minutes attached to this event. Show them.
    • 08:45 08:50
      ACE and HE 5m

      Week 19:

      • Finalise dismantling of green I-beams
      • Start with dismantling of light structure

      Week 20:

      • Finalise dismantling of ight structure
      Speakers: Jordi Bossy (CERN), Yann Denis Robert Seraphin (CERN), Yannick Grislain (CERN)
    • 08:50 08:55
      Integration 5m

      Week 19:

      • Finalise integration of vac pipes passing through RILIS
      • Finalise integration of cables passing through RILIS
      • Confirm space for shielding blocks inside of RILIS
      Speakers: Badr Benhamou, Jean-Pierre Billon-Grand (CERN), Vincent Barozier
    • 08:55 09:00
      STI and HE 5m

      Week 19:

      • Finalise removal of lead inside of RILIS
      Speaker: Laura Lambert (CERN)