RILIS works in Aug

Europe/Zurich
    • 11:30 11:50
      discussion 20m

      Due to approval of drawings for the platform, construction has been delayed from July to August-Spetember

      • construction of the first floor is priority and will take place in August
      • concrete will be poured first week of September (once company is working again after summer break)
      • second level of platform needs galvanisation which cannot be done before/in August
      • second level could be installed (if ready) in 2nd week of September 
      • if not ready, we could start COLLAPS tests (~max 4 weeks) but would then need to find a place to store the platform pieces
      • to be checked: could I-beams fit into the ISOLDE SAS? If no, would there be an alternative for temporary storage?
      • we will come back with more detailed plan in early/mid August when we have a better overview