Due to approval of drawings for the platform, construction has been delayed from July to August-Spetember
- construction of the first floor is priority and will take place in August
- concrete will be poured first week of September (once company is working again after summer break)
- second level of platform needs galvanisation which cannot be done before/in August
- second level could be installed (if ready) in 2nd week of September
- if not ready, we could start COLLAPS tests (~max 4 weeks) but would then need to find a place to store the platform pieces
- to be checked: could I-beams fit into the ISOLDE SAS? If no, would there be an alternative for temporary storage?
- we will come back with more detailed plan in early/mid August when we have a better overview