RF POWER UPGRADE AT JEFFERSON LAB

8 May 2012, 11:00
30m
Danfords Hotel & Marina

Danfords Hotel & Marina

Port Jefferson, New York, USA
Oral Session 1

Speaker

Richard Nelson (Jefferson Lab)

Description

Eighty RF positions are being added to the existing 340 as part of an energy doubling upgrade at Jefferson Lab. Built around a newly designed and higher efficiency 13 kW klystron developed for JLab by L-3 Communications, each new RF chain is completely revamped because of increased power capabilities, yet needed to fit into an existing footprint. This paper will discuss the main components of the new systems including the 13 kW klystron, waveguide isolator, and switch-mode HV power supply, plus installation and operational results so far

Author

Richard Nelson (Jefferson Lab)

Co-author

Mr Andrew Kimber (Jefferson Lab)