121st Impedance Working Group meeting (mandate and workflow)
Date: 07/10/2026
Present: C. Antuono, R. Calaga, E. De La Fuente Garcia, G. Favia, P. Krkotic, A. Kyriakidou, E. Macchia, M. Marchi, I. Mases Sole, N. Mounet, M. Neroni, H. Pommerenke, J. Ruf, H. Schreiber, C. Zannini
IWG: mandate and workflow (C. Zannini)
Discussion:
Patrick asks if we will merge in the IWG all the meetings about future accelerators. Carlo replies that working on future machines is part of the IWG mandate; the FCC impedance meetings have a different scope, but the merge already happened in a sense, since we always use the same slot at 9 on Wednesdays. Carlo adds that it will also include LEP, and he invites Nicolas to present about it in the future.
Patrick asks about the definition of the OSAR table: he wonders if we should always separate device owner and impedance evaluation responsible, since he is the one responsible for impedance evaluations in the Vacuum Group before studies are taken to the IWG. Carlo replies that the two roles can be covered by the same person, but Chiara adds that when doing the instability studies it is possible that the IWG needs to review something, so Carlo adds that the impedance responsible needs to coordinate and follow-up, so it always makes sense to have (at least) two people in the OSAR table. Carlo adds that Patrick's work already falls in the preliminary assessment, but the IWG needs to then do a full assessment, considering also stability and power loss. Chiara adds that, as in the FCC case, even if we have the preliminary assessment we need to have a global look (e.g. crosstalk study).
Mariangela asks if steps 2 and 3 can be done in a different order, Carlo replies that steps 1 to 3 go together and are not necessarily sequential. She also asks who decides the impedance evaluation responsible: Carlo says that it is discussed in the IWG core meeting.
OSAR table
HL-LHC
- BGI: BI is now working on it, as equipment owner was asking for major revision of the design, on the overall geometry, materials and matching network; this will go back to the IWG once a new design is finalized. Carlo asks Mariangela if she is following it up. She replies that she is, together with her supervisor; there were some changes in the design and evaluations of the impedance, the design will be kept internally until they verify that it is compatible with functionality. Carlo says that she should be added as device owner contact.
- TCLD: measurements ongoing about spikes observed during high intensity run. Chiara adds the measurements are on a spare device (on new fingers they produced), and the TCLD was removed but they need to perform measurements to check the radiation levels.
- HL-LHC collimators: presentation by STI at 119th IWG meeting on planning of measurements for next year; IWG waiting for equipment to be ready for measurements.
- TWO-CRYST: studies by Hannes Schreiber, he could present them at an IWG meeting in the future. IWG waiting for feedback from equipment owners. It was approved to keep the TCCP (by both Vacuum and STI) and the Roman Pots too.
- Alice chamber consolidation: presentation in one of the last IWG meetings, now step 0 with Patrick (equipment owner). Carlo asks Patrick when they will have a design acceptable from equipment side, Patrick says that they are waiting to hear from the experiments and for the company to give a mechanical drawing of the possible bellows, so the model is not complete at the moment.
- Roman pots for CMS: already one iteration with IWG, now waiting for equipment owners on issues on cooling of the ferrite, no follow-up to be done at the moment by IWG.
- Crab cavities BPMs and BWS series, measurements scheduled for 2027 and 2028.
- MKIcool tank: still three tanks to be installed during LS3; measurements scheduled, Giorgia says that it is ready and we can start even before next week.
Injectors:
- SPS BGI: discussion on replacing NEG coated cathode with stainless steel cathode after Julian's studies, to be followed up with C. Pasquino.
- MKP-S : more critical due to flat top instability, check if strictly needed. Carlo says we will study the data of this year and then at the restart we will check how things are going; we will be limited so we might consider some mitigation option during Run 4. Giorgia says that from their side improvement of thermal and mechanical behaviour, maybe they can relax a bit the thresholds; the limitation is mainly mechanical. Carlo adds that there can be experimental tests in 2029, when LHC off.
- MKDH: presentation later, ECR circulating.
- SPS BSRT: BI review last week, there will be impedance studies needed. Planning from equipment owner side will be presented at the next IWG by D. Butti.
- Some PS devices: on waiting.
Mariangela adds that there is a study on RF pickups of the SPS, she is performing the consolidation and characterization, together with longitudinal impedance evaluation and power loss studies with HL-LHC beams. Michela says that if they ask for it, it will be evaluated within the IWG.
SPS MKDH impedance considerations (C. Zannini)
Discussion:
Giorgia comments that they will modify the ECR to include this presentation. Giorgia asks about if the permittivity was characterized; Carlo says he only used the permeability in the equivalent model, the one from Maria's presentation. Giorgia asks if the model includes the connecting transition from chamber to pipe. Carlo confirms that it does not include it, and it is assumed open ended (matched) and referenced to ground.
Hermann asks if an anisotropic material is used, Carlo says that they use equivalent properties of the laminated steel, so an isotropic material. If we want to improve the model, then we have to include also these properties. Since this is not a usual ferrite kicker but a laminated steel kicker, so the properties are very different; what we got looks reasonable.
PS KFA4: Installation of an Inductive Adder Pulse Generator (M. Neroni)
Discussion:
Carlo asks if it is on EDMS, Michela says that it already went through. Michela asks if there is going to be another ECR after the testing of the inductive adder in the lab, Johannes says that he does not know about a second one; some high frequency VNA measurements can be done in the future. Johannes does not expect any significant resonances to be added and he highlights that is is not trivial to know the exact cable termination when the switch/diode configuration is connected. He mentions that this could be probably represented by a capacitor when not pulsing. However, the inductive adder termination is not expected to have a worse impact on the impedance than the current open circuit case. Carlo says that probably the length of the cable helps a lot, together with the attenuation. Similar measurements were already discussed in the past, they would be interesting.