B-Train LS3 Work Kick-off

→ Europe/Zurich
311 meeting room (CERN)

311 meeting room

CERN

B-Train Kick-off meeting

Present: Miguel, Martin, Alberto, Unai, Carlo, Matthias, Marco

Transfer lines: Alberto will come back from a discussion from Mathew phraser on Friday to decide what to do

PSB: NMR cleanup, FMR recabling, amplifiers, chassis. UNai: Worth checking to redo it in a better way

PS: Fluxmeter: Ongoing development, green light from Attilio. Check if we can install fluxmeter parasitically

SPS: Check if it is possible to power during LS3

LEIR: Check, given the model if there are points for additional sensors to fully validate the model in order to get the integral from the model.

LEIR: Check run with different ion types

ISOLDE: Slow control, no need for new electronics.  Action: Firgure out who is implementing the FGC control Ready by Q4 2027 (either reimplement HRS class with new FGC, or new control) Additional: Continuous RT control for R&D. See available ressources (FTE?). Decide what to do with ISOLDE money (electronics, People)

Transferlines: Alberto checks what sensors need to be done.

Instrumentation: SPS fluxmeter as backup, not baseline

Action: Buy DI/OT

 

There are minutes attached to this event. Show them.
    • 15:30 → 15:50
      B-Train End of Run and LS3 general timeline 20m

      Some information on the end of Run3, statistics, reliability, Problems, annoyances.

      Timeline for LS3 for each machine

    • 15:50 → 16:10
      Work to be done, Resources and Status 20m

      Current open points for restarting operation after LS3

      • Electronic racks and cleanup
      • WR timing
      • Gateware, Software (Fesa)
      • Ucap monitoring + WRAP dashboards
      • Alarms, Automated fault detection
      • Diagnostic agent skills
    • 16:10 → 17:10
      Proposed Upgrades and improvements

      Non-necessary upgrades and improvements

      • Fluxmeter changes
      • instrumentation
      • Online algorithms
      • etc.