39# MuCol Management Committee
Deliverables:
-------------
**31 Oct 2026**
D12 (5.1) Report on collider ring design
D14 (6.1) report on design of high power and high efficiency RF power sources à if extended: 30 Apr 2027
**30 Nov 2026**
D8 (3.1) report on parameters and initial study for the Proton Complex
D13 (5.2) Report on the design of the HEC
D15 (6.2) Report on RF for MCC and HEC
D17 (7.2) Consolidated report on muon collider magnets
D22 (1.8) Data-management Plan - Updated Version
D11(4.3) Consolidated Report on key subsystems à if extended: 31 May 2027
**28 Feb 2027**
D24 (1.10) Policy Brief Document - Updated version
D5 (1.5) Consolidated ESPPU report à if extended: 31 Aug 2027
- Milestones:
-------------
**28 Feb 2027**
M13 Publication of report of detector performance with major physics process at several ECM