HIE ISOLDE CM1 refurbishment coordination meeting
Present:
Alexandre Beynel, Alexandre Dorsival, Beniamino Di Girolamo, Jean Baptiste Deschamps, Jose Antonio Ferreira Somoza, Graeme Barlow, Guillermo Merino, Maria Carmen GIordano, Rory Sutherland, Yann Leclercq
Summary of the discussion:
WV presented the current status and the plan through the end of November. The next milestone is cryomodule venting, with RP checks planned for the beginning of December.
Venting will follow the same procedure as for CM4, using a filter. The feasibility of this approach was confirmed after the meeting.
JB points out that we need to check whether we have enough spare kolsterised fasteners, as some will likely need to be broken to open the flanges, particularly those on the DN16 thermal shield connections and the DN63 cavity helium connections. We also need to check whether additional CERNOX sensors or other instrumentation should be prepared. (Action: Walter to check with Daniel V.)
GB notes that, to protect the assembly during the winter break, we can place it back in the VVTS assembly after removing the RF cables and instrumentation. Given the schedule, this appears to be the most appropriate course of action.
YL notes that the cavities should be removed without loosening the supporting frame, in order to preserve the alignment.
WV explains that three spare cavities are available for use. The remaining two must be recovered from the cryomodule and undergo a reprocessing cycle lasting at least five weeks, resulting in a waiting period before they are ready. We can either begin assembling the three available cavities or wait until all five are available. The latter approach would better preserve the cleanliness of the spare cavities, which could remain packaged, but seems less time efficient. However, mounting the cavities takes only a few days, so we can probably wait until the last cavity has been tested before starting to mount the first four, without losing time, as the last cavity will still require a final rinse.