LS3 activities concerning BE-GM and TE-MSC
Activity 1)
Request to release the W-bellow clamps for re-alignment and stress relief of several equipment :
- All connection cryostats
- Magnets with a roll angle about a certain criteria (for the moment exercise done with 9 mrad, to be clarified)
Only the clamps on the side of the rigid sleeve to be released (opposite to the side on which we slide the bellow)
Activity 2) Jacks out of range, Q10R6 + MB.B21R6
- P6 issue - Meeting in 2027 to make a proposal to LMC
- MB.B21R6 - Proposal is to take one jack from the stock and remove 1 or 2 mm from the base plate. To be checked how to remove the existing jack (maybe by controlled lifting by BE-GM)
Activity 3) D1 at P2/P8
- Inverse banana shape. To be cross-checked with ABP if this is an issue for aperture. Does not seem so, since D1 is the LHC magnet with the largest apertuer
Action items:
1) MSC to check with VSC if the clamp release can create a risk for the joint integrity and bring some NCs
2) MSC and WGA to define a clear criteria for the limit roll angle
3) Based on (2), BE-GM will review the magnet table
4) MSC to check with BE-ABP the aperture of D1
5) Once a clear plan is established, check the LS3 planning and try to see how all this additional work fits. Then proposal to be transmitted to EN-ACE. Preferably activities to be scheduled in 2027