IBDRS CV pipes on 170 roof
Good afternoon,
I am sending a summary of today’s meeting.
Estimated duration of works:
- Scaffolding works: 3 days
- CV pipework: 6-8 weeks
We have 3 options for the dates for the installation of the pipes on the roof of B. 170:
Option A: we start in April 2027
CV would install the pipes in the concrete gallery (the once that will serve as ducts for LS4 ). The duct is planned for week 16 (19.04-23.04 ODM 36873006) so the works on the roof would start in week 17 (26.04.27) with the scaffolding up the week before.
Option B: We start in week 24 (14.06.2027)
CV works will take place after the Civil engineering crane will be taken down and the scaffolding will go up the week before (week 23)
Option C: we start in week 36 (6.09.2027)
CV works will start after the soil is placed on the hill with the scaffolding up the week begore (week 35)
To see which option is feasible we would need the flowing:
@Guillaume Paul Cnudde – please check with you contractor, safety, and the transport service for option A – if it is possible for there to be 2 cranes working at the same time. Please also check for option B if there is a possibility to change the way the trucks will arrive to dispose of the soil on the hill.
@Fabio Cicolini and @nicolas.petiteaux – if you could please make a document describing the order of works and the crane schedule for the works as we discussed today. We would need to know when and how long you would need the crane.
I also wanted to ask if you will need a scaffolding for the part of the works next to B. 197 (pictures below) as the support is in place on the side wall?
I propose we have the deadline of the 4.12.2026 to discuss again so if you could please send me all the necessary information by then.
Please let me know if you have any questions.
Regards, Nina