Speaker
Nicolas GILBERT
Description
Following the particular extended shutdown of 2004/2005, the main activities on the
SPS machine will be presented, focusing on the few activities which could impact on
a "standard" restart.
A simplified planning shall be presented, underlining the overlap time period
during which the hardware tests will be carried out in parallel with the completion
of some installation activities.
Finally, the access to the SPS machine during this particular test period and the
link to the future INB rules shall be briefly described.
systems