- J&E Hall intervention on 8/10/12?
- status of the connections
Speaker:
Olivier Crespo-Lopez(CERN)
11:00
→
11:10
Brine skid + piping10m
- brine skid: info from SXL1 (Cyrill)
- brine piping installation (Daniel)
- brine diaphragm flowmeter (Pierre)
Speakers:
Cyril Degeorge(I), Daniel Lefils(CERN), Pierre Bonneau(CERN)
11:10
→
11:20
C3F8 Condenser Installation10m
- Steel structure on the SH1 roof: cost and delivery time (Michele)
- Condenser supply: pipe support problem (Enrico)
- Mechanical installations around the condenser
- Degassing system (Cyrill + Pierre)
- purchase of the small valve for slow liquid filling (Pierre)
Speakers:
Cyril Degeorge(I), DrEnrico Da Riva(CERN)
TS electrical cupboards construction advancement10m
- end of the electrical cupboard construction
- delivery time for the power cubicle form CCM (Olivier)
Speaker:
Florian Corbaz(CERN)
11:40
→
11:50
Instrumentation10m
Speaker:
Pierre Bonneau(CERN)
11:50
→
12:00
USA15 "balcony" assembly status10m
- Skids installation in USA15: transport problems (Olivier)
- document of SC for the weight the structure can support (Jose)
- leak test in bdg 298
- drawings for the installation of the components on the balcony structure (Cyrill)
Speakers:
Cyril Degeorge(I), Pierre Bonneau(CERN)
12:00
→
12:10
Electrical Power Supply and Cabling10m
- new version of the Electrical requirements document (Jose)
- HP connection EN/EL: advancement status (Wislaw)
- Jan: LP + instrumentation connection: Sergei Malukov advancement status. (Jan)
Speakers:
Daniel Lefils(CERN), Wieslaw Iwanski(CERN)