Operations team & Sites

Europe/London
EVO - GridPP Operations team meeting

EVO - GridPP Operations team meeting

Description
- This is the biweekly ops & sites meeting - The intention is to run the meeting in EVO: http://evo.caltech.edu/evoGate/. Join the meeting in the GridPP Community area. - The phone bridge number is +44 (0)161 306 6802 (CERN number +41 22 76 71400). The phone bridge ID is 15 0446 with code: 4880. Apologies: Mark
Minutes
    • 11:00 11:20
      Experiment problems/issues 20m
      Review of weekly issues by experiment/VO - LHCb - CMS - ATLAS - Other
    • 11:20 11:40
      Meetings & updates 20m
      With reference to: http://www.gridpp.ac.uk/wiki/Operations_Bulletin_Latest - Tier-1 status - Accounting - Documentation - Interoperation - Monitoring - On-duty - Rollout - Security - Services - Tickets - Tools - VOs - SIte updates
    • 11:40 11:55
      EMI-2 migration (status) 15m
      - including WN situation End-of-life situation: gLite 3.2 30-11-2012: WN, DPM, LFC, glite-GLEXEC_wn, UI, FTS EMI 1 (http://www.eu-emi.eu/releases#MajRel) 30-10-2012: end of standard updates gLite 3.2 dCache/WN/DPM/LFC/FTS(?) from 01-12-2012: Nagios probes returning CRITICAL by 17-12-2012: Upgrade plans requested from site administrators by 31-01-2013: Services must be decommissioned from 01-02-2013: end points still deployed go in downtime
    • 11:55 12:05
      GDB overview 10m
      - See Ewan's email last week which is now also in the wiki reports page https://www.gridpp.ac.uk/wiki/GDB_14th_November_2012.
    • 12:05 12:10
      Update on post-EMI proposal/discussions 5m
      - There was a WLCG-EGI discussion on repository needs - see attached document. - The proposal was discussed at the PMB. The PMB need a list of 'mission critical' issues to decide on what action needs to be taken. These would include areas that will be lost with the current plan or clear calls on additional effort.
      document
    • 12:10 12:11
      AOB 1m