- offer for the brine skid insulation (Daniel)
- offer for the balcony unit insulation (Daniel)
- cost to completion estimation for the scaffolding (Daniel)
- cost of the chiller(s) roof
- cost of the condenser roof
Speaker:
Jose Antonio Botelho Direito(CERN)
Slides
10:20
→
10:30
Urgent matters10m
- DN50 C3F8 pipe pressure test on Monday 3rd @ 5pm.
- Kenoll flanges waiting time!!
- Transport: disentangle the condenser transport to the rest (buffer tank, valves etc.)
10:30
→
10:40
Water skid and water piping installation10m
Speaker:
Stefano Moccia(CERN)
10:40
→
10:50
Brine skid + piping10m
- DELTA Ti brine piping installation (Daniel)
Speaker:
Daniel Lefils(CERN)
10:50
→
11:00
C3F8 Condenser Installation10m
- Condenser delivery (Michele)
- Mechanical installations around the condenser (Pierre)
- Degassing system (Cyrill + Pierre)
Speakers:
Cyril Degeorge(I), DrEnrico Da Riva(CERN)