Ben - Locate platforms to be mounted on VacTank to reach out to the HPDs, and present them to Michel for visual inspection
-
Ben- Check whether the RBX supporting structure (90cmx90xm) can be fitted in a cherry picker with 2 people on board
-
Ben - Provide Stephane with a summary of the inventory items to be removed from the UXC55
-
Ben/Sasha - carry out a cost/benefit analysis focused on the possibility to move YB+2 over the edge of the VacTank, exposing the BPipe. Design and installation of dedicated BP protections will take time and will be the responsibility of HO