CLIC DBQ Permanent Magnet design Status Meeting

→ Europe/Zurich
30/6-019 (CERN)

30/6-019

CERN

20
Show room on map
Slides
CLIC DBQ PM Version Status Meeting
Presents (WebEx): J. Clarke, N. Collomb, Ben, Sheperd, M. Modena, A.Bartalesi, A. Aloev, M.Struik (partially):

MINUTES:

1st Prototype status:


- Antonio and Michele presented the Report on the mechanical and magnetic measurements on the 1st Daresbury prototype delivered (High Gradient range). (Report attached to the Meeting Minute).
- Discussion on the different analysis and hypotesis of its mechanical behaviour when operated.
ACTION ANTONIO: send the .xls file of the measurements.

- Rotating coils measurements expected for next week (TBC after decision of MM colleagues).
ACTION MICHELE: keep Daresbury informed on activities.

- Confirmed that after the rotating coils measurements, the prototype will be sent back to Daresbury. There it is planned to have a complete fringe filed mapping (by Hall probe measurements).

2nd Prototype status:
- Components procurement ongoing, the majority will arrive before the Summer.
- Discussion of expected (FEA computed) deformation respect to the 1st prototype (FEA calculation report attached to the Meeting Minute).

Next Meeting to be fixed after 1st prototype measurements.