Video conference to discuss the strategy of the 11 T Dipole project
Agenda:
1) Follow up from the last meeting. Status on mechanical analysis and mechanical models
2) Recap results on last 11T short model and feedback on design/construction. What was learned ?
What will be changed in the next model at FNAL ?
How is the lesson being transferred to the first CERN Model?
3) What is the status of compatibility studies between the two design ? Is it conceivable that a US-coil and a CERN-coil can live in the same 2-in-1 structure ?
4) Sketch of new program in view of the new situation with funding in the US (i.e. transfer of funding form GARD to LARP and MAP). Sasha is proposing a short-magnet program in the US, at least for next year. Does that fit the needs for 11 T ?
Is it conceivable to develop a program where coil technology is developed in the US and length extrapolation is investigated at CERN ?
Can we test a "blind technology transfer" in making coils ?