PMB meeting
2008-Mar-11, 10.10-10.45 CET
Attending: Aake (minutes), Norbert, Lauri, Katrina, Zofia
Excused: Mario, Florida, Algimantas
Next meeting: March 18, 10.00 CET
Minutes
-----------
1. BalticGrid-II - current status
a) ALMOST Passed the negotiation phase, signatures collected and sent
to Enric (Feb 18).
b) Will get a formal letter that the negotiation phase has been passed
from Enric once the signatures arrived to Brussels
c) Monika Kacik new Project officer of BG-II
d) Status BG-II Grant Agreement comments from partners:
KTH Sweden
EENET Estonia ok
NICPB Estonia
IMCS UL Latvia
IFJ PAN Poland ok
PSNC Poland ok
VU Lithuania
RTU Latvia ok
ITPA Lithuania
CERN Switzerland ok
NICH BNTU Belarus ok
UIIP NASB Belarus ok
VGTU Lithuania incorrect address and title - to be corrected
--> All partners to answer (or explain why the delay) by today Tuesday.
2. EU Review – planning of preparation - Suggested DATES confirmed
Persons to attend the EU review:
- All activity leaders
- OD (Mario)
- Representatives from the partners not having an activity leader:
Florida or John from CERN, Grazina from ITPA and Ilmars from RTU - ok?
- Inger Karlsson (finance)
Demos:
- Algimantas to prepare two stand alone (.avi files) demos, each of
2-5 minutes long.
One of these will be used in the review.
Dates and place decided.
+1st rehearsal - see information on accommodations from Zofia
- April 17-18
- Kracow
+2nd rehearsal
- May 26, starting in the morning, all to fly in on Sunday
- Brussels
- Lithuanian Embassy - confirmed (Algimantas)
- Hotel: www.st-nicolaus.be
--> All to stay at this hotel.
+ Review
- May 27, Brussels (details expected from Enric)
3. Deliverables PM26 and PM27 - DJRA1.5.
--> DJRA1.5 ready for internal review, PMB comments by end of this week.
- DNA3.10 (P28, VU) "Report on applications’ production quality",
including MNA3.13
Moderator: Lauri
Reviewers: Appointed by Lauri
Status: ready for review by end of this week.
Time plan:
Send document link to Moderator: Feb 31, 2008 (late)
Moderator to send final decision to PMB: March 28, 2008
PMB to send final version to EU: April 05, 2008
4. Changed dates for the final deliverables and milestones (due to
review):
Reason of change of date: Deliverables need to be sent to reviewers
two weeks in advance to the review.
DNA1.1 (?), DNA2.7, DNA2.8, DNA4.5, MNA3.14, MNA4.4, MSA1.6, MJRA1.7,
MJRA1.8
----> TOC to PMB March 20, 2008 -> Feb 28, 2008
Send document link to Moderator April 30, 2008 -> April 18, 2008
Moderator to send final decision to PMB May 28, 2008 -> May 06, 2008
PMB to send final version to EU June 05, 2008 -> May13, 2008
5. BalticGrid-II kick-off meeting
Date: May 13-15 (starting after lunch on May 13, ending at 3 pm on
May 15)
Place: Central Vilnius, most probably at the old campus of Vilnius
University.
6. AOB
6.1 Invite new BG-II partners to PMB in early April
6.2 Tuesdays at 10.00 CET a good time for PMB, or should we move it?
6.3 Travel budget and how to report travels in BG-II - need to be
identified before signing GA.
--> See mail from Aake (March 11)
6.4 Open the web for our new (BG-II) partners
--> Zofia to prepare Robert for this
--> Aake to mail BG4Science mailing list about this
6.5 Tycoon issue
- Norbert got feedback and promises (to become open source) from HP
- Problem with stability in general (never better than beta versions)
- Kristaps Dzonsons to get in contact with HP to get full Tycoon version
- I parallel searching for alternative solutions for BG-II
- No pilot will go into BG-I/SA1.
Aake
--
Aake Edlund, PhD
Mobile: +46 (0)70 662 15 10
- Associate Director Swedish National Infrastructure for Computing
(SNIC) - International Coordinator
- Project Director BalticGrid
- Senior Project Manager, KTH/CSC/PDC
_______________________________________________
balticgrid-pmb mailing list
balticgrid-pmb@lists.eenet.ee
https://lists.eenet.ee/mailman/listinfo/balticgrid-pmb
There are minutes attached to this event.
Show them.