The presentation will cover updates for these action points:
1) Follow-up on mirror delivery to avoid installation delays
2) ECR for option ‘B’ to be submitted to EDMS
3) Continued RF testing and simulations to be scheduled
4) Freeze optical design with number of motors
5) Provide draft software specification whenever possible (final Sep 2014)
6) Light shielding