1) Update on schedule:

Latest official one can always be found here: https://espace.cern.ch/be-dep/BEDepartmentalDocuments/BE/LHC_Schedule_2015.pdf

- Cold check out requirements for BI (Bernd in contact with Rossano)

- Plans for beam commissioning to be specified

- LHC (draft!) MD requests by 20/02 (realistic?) - first MD block end of July 2015

- First BI LHC commissioning meeting this Friday in the CCC (E. Bravin to chair)

2) LHC BSRA (Stefano)

- Installation finished

- Low-level software implementation on-going

- Question about periodic checks to handle calibration of PMT to be decided with OP/ABT etc

3) LHC BSRL (LDM)

- Question of best suited detector (APD or Hybrid) to be decided with beam (B1 only equipped)

- BI/TB proposal to order another Hybrid detector with an operational spare (BSRT budget)

- Electronics and software to be decided in dedicated meeting (PM/SW)