Alberto Di Meglio (CERN)
Description
Conference Name: ETICS Technical Committee meeting Recurrence: Every Thursday at 15:30 Dial-in numbers: +41227676000 (Main) Access code: 0126137 (Participant) Participant site: https://audioconf.cern.ch/call/0126137
Minutes
    • 15:30 → 15:35
      Welcome and headcount 5m
    • 15:35 → 16:00
      Status reports 25m
      Highlights of the week, 5 minutes for each WP (NA2, SA1, SA2, JRA1, JRA2)
      • NA2 5m
        • Sent proposal of User’s Questionnaire ... any comments? • Written article for EGEE 2008 booklet and sent to PMB 9th July. New version considering feedback will be sent today. The article will be submitted on Friday 11th. • Collaborated with SA2 on the FAQ. New FAQ were created and the others were checked after they had been added to the portal. Adriano will write something on Grid-QCM to add to the Knowledge Base section of the user support portal.
      • SA1 5m
        + SLS monitoring: The ETICS services monitoring has been shut down at INFN. Actions has been taken to re-establish the service at CERN however did not lead to full success due to internal troubles of SDB and expert being not available at a time. For the moment the INFN setup has been re-established. + Periodic submission (cron-based) When waiting for the ETICS Scheduler a periodic cronjob has been set on another node and is being tested + Release Candidate: etics1 + etics2-repository Updated several times with NMI scripts that have been fixed. + Time synchronisation: some problems with images running in virtualized env. on newly allocated hardware (soon solved with nntp and cronjobs) + Creation of images for RHEL4 (ia32, x86_64) - on hold - licence issues + Virtual Nodes Management Prepared page describing the Virtual Images management (updates, modification). Available under: https://twiki.cern.ch/twiki/bin/view/ETICS/SA1VirtualizationVMManagement + Metric Disseminator Created the configuration etics.dissemination-trend-analysis_R_0_1_0 containig bugfixes, refactoring, the changes to the interface, and a couple of enhancement discussed previously. This should be the future line of development for the disseminator. http://etics.cern.ch/rundir/etics-dissemination-trend-analysis_R_0_1_0_x86_slc_4_build/reports
      • SA2 5m
        Support --------------- - Valerio/Robert in shift. 3 tickets for ETICS Infra, 2 solved, 1 escalated. TPM making a lot of wrong assignment. Experts need to be careful. I'll complain with GGUS TPM. - Support portal available at etics-08.cnaf.infn.it. The aesthetic is not final, we'll aling it ot the web site. Also the contents aren't, I need to write the frontpage, we still have to complete the FAQ, and the initial articles needs improvements. Nonetheless it allows for making an idea of what's going to be. Please comment. Infrastructure Integration Job Submission ------------------------------------------- - Had meeting with gLite SA guys to train new people on gLite's job submission. Started working on tech details how to represents ETICS jobs as JDL. New Applications ----------------- - Continued integrating UNICORE, and started thinking about other HPC applications. Understood EGEE structure to ask for possible new applications. Evaluation and requirements --------------------------- - Started analyzing first use cases and requirements collected among gLite developers. - Installing ETICS services to be able to do the evaluation. Working with Marina so that the experience can be resued when making the installtion procedure easy enough for the services to be deployed by others. Various -------- - Beta client testing and feedback collection. Some suggestions sent to Alberto.
      • JRA1 5m
        Nothing to report
      • JRA2 5m
        Deliverable The internal review version of the deliverable DJRA2.1 is ready and it was sent to internal review. Unfortunatelly, this deliverable required more work than expected. Metrics-GridQCM The document sent by us last week has been updated. We rarried out a quite thorough study on the required metrics and the available rules that the plugins can calculate. The rules provided by ’cyleheckst’, ’pmd’, ’CodeWizard’ that resemble the required metrics have been identified. Development of JRA2 services Development of JRA2 services are in progress - in initial phase. Experimenting with GWT features, working on plugin creation wizard, experimenting with Gridsphere-based workflow editor and gwt based testsystem integration. Esentially it works, but requires more work to be integrated properly. Plugins for D4Science D4Science (Paolo Fabriani and Andor Dirner) is now integrates the plugins in the build of gCube. In the current version of ’findbugs’ plugin (which is in production) we found some directory mismatch problems causing that html reports are not created. I can correct it. They requested some mechanism not to write the name of profile for every individual component. Question to Alberto: Is it possible to attach the profile just for the subsystem, and then individual components inherit it?
    • 16:00 → 16:05
      Deliverables status 5m
      Update on deliverables status for PM3 and PM4
    • 16:05 → 16:15
      ETICS presentation at PSM 10m
      Feedback after the presentation
    • 16:15 → 16:25
      ETICS USIS (User Satisfaction Improvement Strategy) 10m
      Improving user satisfaction about usage of the ETICS services is critical. ETICS is often perceived as slow and difficult to use. This is due to a number of factors: 1) Need for technical improvements in speed and usability 2) Disinformation or third-party rumours 3) General resistance to adopt 'procedures' We need to understand what to focus on and have a plan to address this issue as a combination of technical enhancements, training and dissemination. Where to start?
    • 16:25 → 16:30
      AOB 5m