Participants:
* K. Elsener, I. Ahmed, E. Adli, D. Schulte, F. Antoniou, B. Jeanneret, T. Lefevre
DS:
* In two weeks we will have a review of what is needed for the Beam Instrumentation Templates
BJ:
* Presented "Specification of Vacuum System of the Drive beam long transfer line"
- BJ comments: specification should not contain the physics or justification, just the specification
- a spec must always conform to the "project breakdown structure (PBS)
- this spec: based on BI instrumentation spec docs
- DS comments: not clear if tune shift/spread is a problem for a transfer line (unlike a ring) [so less emphasize should be put on this]
- KE: r = 10cm all along beam line? JB: yes. TL: is this the min? JB: yes.
EA, 28-may-2008