LIU - Planning & Installation meeting

Europe/Zurich
30/7-010 (CERN)

30/7-010

CERN

20
Show room on map
Minutes
    • 16:00 16:10
      Follow-up on the ECRs 10m
    • 16:10 16:30
      ECR - PSB: Booster Injection Transfer Line Magnet Changes PSB-L-EC-0001 20m
      For the 160 MeV beam injection into the Proton Synchrotron Booster (PSB), several magnets need to be changed in the Booster Injection (BI) transfer line to cope with the increased beam energy. Also, considering the age and condition of the remaining magnets and profiting from the occasion the change of the remaining magnets is proposed for consolidation reasons.
      Speaker: Antony Newborough (CERN)
      document
    • 16:30 16:50
      ECR - PSB: Upgraded PSB Distributor BI.DIS10 PSB-MSMIA-EC-0001 20m
      During the installation of the new H– injection system in the PSB, the currently installed BI.DIS system will be removed and replaced by the new BI.DIS10 system. This replacement includes a new vacuum tank with five pulsed ferrite core magnets in the BI line, the Pulse Forming Network (PFN) in building 361 as well as the power cables connection both
      Speaker: Wim Weterings (CERN)
      Slides
    • 16:50 16:55
      AoB 5m
      • ECR - PSB: New KSW16L1 in the PSB Machine 5m
        Installation push back to the 2016/17 YETS?
        Speaker: Antony Newborough (CERN)