Aim:
- to discuss ‘LIU / HL-LHC’ interface subjects
- to discuss possible improvements (strategies, equipment improvements, schedule, beam parameters) beneficial for both projects
- to clarify misunderstanding and identify parameter mismatch
- to update parameter tables if needed
- to ensure coherency of timeline and decisions between the two projects (e.g. ions)
14:30
→
14:40
Session 1 – C&S review outcome10m
Speakers:
Giovanni Rumolo(CERN), Oliver Bruning(CERN)
Protons: Updates on LIU baseline and options (incl. staged implementation), schedule2m
Protons: Updates on HL-LHC baseline and options (incl. staged implementation), schedule2m
Ions: Updates on HL-LHC baseline and options (incl. staged implementation), schedule2m
Ions: Updates on LIU baseline and options (incl. staged implementation), schedule2m
14:40
→
14:50
Session 2 – 2015 operational experience10m
Speakers:
Hannes Bartosik(CERN), Mike Lamont(CERN)
Linac4 status – any changes for HST, LIU parameters, schedule?2m
Proton beam operation and MD in the injectors – outcomes for LIU and HL-LHC?2m
25 ns operation in the LHC – consequences for the LIU and HL-LHC?2m
Ion operation in the injectors2m
14:50
→
15:00
Session 3 – Shutdown planning10m
Speakers:
Beniamino Di Girolamo(CERN), Katy Foraz(CERN)
Work to be done in Run2 YETS and EYETS, including de-cabling, for LIU and HL-LHC2m
Work to be done in LS2 (LIU and HL-LHC anticipated), and LS2 length2m
Work to be done in LS3 (LIU delayed and HL-LHC) and LS3 length2m
Overview of other projects including CONS2m
15:00
→
15:10
Session 4 – Beam tests in injectors needed for LIU and HL-LHC10m
Speakers:
Rhodri Jones(CERN), Verena Kain(CERN)
Joint LIU / LH-LHC MD needs in the injectors5m
Equipment installation needed from CERN projects in the injectors:5m
o Crab-in-SPS: needs, integration studies, timelines
o Collimators in SPS: needs, timelines
o Instrumentation in SPS
15:10
→
15:20
Session 5 - Other possible non-baseline improvement towards reaching target goals (beam parameters and luminosity) and implications10m