PH-ESS is now ready to discuss your 2005 requirements for crates under the contract with Wiener. The arrangements will be very much as for 2004, but there are a number of important technical and commercial issues we would like to explain and discuss with users.
transparencies
10:00
→
10:20
Introduction20m4-R-017
4-R-017
CERN
Speaker:
Paul Harwood
10:05
→
10:25
Technical overview20m4-R-017
4-R-017
CERN
Crate configurations
Water cooling
Radiation and magnetic field tolerance
10:10
→
10:30
Procurement procedure20m4-R-017
4-R-017
CERN
Spares
Schedule with deadlines
Advance payment
Order ammendments
Additional costs (transport & exchange rate)
Onward shipping (outside CERN)